2Q FY24 Quarterly Report & Appendix 5B
Released
Released
Announcement PDF
Q2 FY24 Quarterly Report
29th January 2024
Drilling on the Precinct at South Erregulla
Comments from Managing Director & CEO, Stuart Nicholls:
“During Q2/24 Strike completed its first quarter of production operations, producing a gross
total of 1.9 PJe, at $0.51 GJ, which generated significant positive cashflows. The quarter was
also marked by completing the acquisition of Talon Energy and delivering appraisal success
at South Erregulla whilst progressing both the South and West Erregulla developments.”
Highlights
Walyering
•
Walyering (L23) produced a total of 1.9 PJe of gas and condensate generating gross revenue
for the L23 Joint Venture of $14.4 million (note STX now owns 100% of L23).
•
Nameplate capacity reached at 33 TJ/d and 265 bbls/d of condensate on 24 December 2023.
•
Strike and Alinta Energy WA Pty Ltd entered into a firm 100% take or pay gas sales agreement
for a total of 3.4 PJ over ~2 years from February 2024.
South Erregulla
•
Successful appraisal drilling at SE3 confirmed the continuity of the South Erregulla gas field
to the Northwest with 13 metres net gas pay. Additionally, appraisal of the potential CO2
storage capacity, observed 75m of net reservoir.
•
Strike secured foundation firm gas sales agreements for a total of ~42 PJ which will underpin
the bankability and development of the proposed Phase 1 development.
•
South Erregulla’s Phase 1 development received its Part IV primary environmental approval.
Corporate
1
•
During the quarter Strike completed its acquisition of Talon Energy Limited via Scheme of
Arrangement consolidating 100% ownership of the Walyering gas field.
•
Strike paid down $6.7 million of its drawn debt with Macquarie Bank and finished the quarter
with a liquidity position of ~$114 million ($67 million of cash and $47 million of committed,
undrawn debt facilities), plus an uncommitted $80 million contingent debt facility for Strike’s
South Erregulla domestic gas development 1.
Uncommitted facility remains subject to lender credit approval.
Strike Energy Limited ABN 59 078 012 745
www.strikeenergy.com.au
P: +61 8 7099 7400
E: strike@strikeenergy.com.au
Level 1, 40 Kings Park Road
West Perth WA 6005
Key Performance Metrics
Sep Q1
FY24
Dec Q2
FY24
Qtr on Qtr
change
FY23
YTD
FY24
YTD
Change
(PJe net)
0.05
1.89
1.84
0
1.94
1.94
(PJe net)
0.03
1.04
1.01
0
1.07
1.07
0.38
14.39
14.02
0
14.77
14.77
0.21
7.92
7.71
0
8.13
8.13
Cash and cash equivalents
103.5
66.78
(36.71)
9.72
66.78
57.06
Undrawn debt
46.75
46.75
-
6.75
46.75
40
Total Liquidity
150.2
113.5
(36.7)
16.47
113.5
97.06
A$ million unless indicated
Sales volume (gross)
Sales volume (net to Strike)
Sales revenue (gross)
2
Sales revenue (net to Strike)
Note: Net to Strike is at 55% equity until 31 Dec 2023. Due to rounding, figures and ratios throughout this report may not reconcile.
Production
Sep Q1
FY24
Dec Q2
FY24
Qtr on Qtr
change
FY23
YTD
FY24
YTD
Change
PJ
0.05
1.81
1.75
0
1.86
1.86
PJ
0.03
0.99
0.96
0
1.02
1.02
kbbl
0.29
14.6
14.31
0
14.89
14.89
kbbl
0.16
8.03
7.87
0
8.19
8.19
Total production (gross)
PJe
0.05
1.89
1.84
0
1.94
1.94
Total production (net to Strike)
PJe
0.03
1.04
1.04
0
1.07
1.07
MMboe 3
0.01
0.31
0.31
0
0.32
0.32
Production by product
Sales gas (gross)
Sales gas (net to strike)
Condensate (gross)
Condensate (net to strike)
Total production (gross)
Note: Net to Strike is at 55% equity until 31 Dec 2023.
Walyering (L23, STX previously 55% now 100% and operator)
2
•
The Walyering gas field produced a total of 1.9 PJe of gas and condensate for the quarter or
approximately 20 TJ/d of sales gas and 159 bbls of condensate.
•
Production above the firm offtake of 20 TJ/d was intermittent due to several episodes of
downstream maintenance on the Parmelia Gas Pipeline, which limited deliveries into Strike’s
existing marketing arrangements, and lower customer nominations during the seasonal
shoulder season for electricity generation.
•
Upstream performance of the field has been observed to be within the range of expectations
and to have a slightly higher heating value resulting in an increased energy conversion from
volume (mmscf to TJ).
•
Strike successfully delivered 33 TJ from the Walyering gas field into the WA domestic gas
market on 24 December 2023 demonstrating the upstream facility’s throughput capacity.
•
Having proven the ability to deliver additional firm offtake, Strike and Alinta Energy WA Pty Ltd
entered into a 100% take or pay gas sales agreement for a total of 3.4 PJ delivered into the
Parmelia Gas Pipeline over ~2 years starting in February 2024.
Sales revenue includes gas banked and not taken or produced pursuant to the ‘Take or Pay’ contract with Santos WA Ltd.
3
Barrels of oil equivalent (boe) and petajoule (PJ) of gas are calculated on a 171,940 boe per PJ energy equivalence basis. The ratio does not reflect the relative commercial value of
gas and oil-condensate. MMboe – million barrels of oil equivalent.
2
•
Subsequent to the quarter end, the Walyering gas field has averaged 23 TJ/d and performed
at a new peak rate of 34 TJ/d for 7 hours on the 23rd of January 2024 without incident before
downstream restrictions forced customer renominations downward. Firm daily production
rates will continue to increase upon commencement of the Alinta gas sales agreement.
•
Strike has completed reprocessing of the Walyering 3D seismic which has substantially
improved the resolution of the field and nearby prospects. Strike is incorporating the new
seismic along with the historical production data to conduct a Reserves and Resources
review with RISC, which it expects to complete in the coming months.
•
Based on the improved nearfield prospectivity, Strike has commenced work in order to
understand what is required to debottleneck the existing plant and what upgrades would be
required to increase the Walyering production capacity to >40 TJ/d. This work has also been
matched with engagements on sending Walyering gas into new markets to meet higher priced
demand around the State.
•
Strike has spent much of the last quarter preparing for the Walyering-7 appraisal well, which
is due to spud late March 2024. Post receiving the reprocessed Walyering 3D seismic, Strike
has relocated the bottom hole location due to identifying attractive structural closure in a fault
compartment to the northeast of Walyering-5.
3
WA Energy Market
4
•
WA gas market conditions eased but
remained elevated with a maximum WA spot
price of $9.47/GJ during the quarter. It is
important to note that, whilst this price is
lower than the previous quarter, it is still
significantly higher than historical pricing
and reflects the consistent underinvestment
that has reduced supply in both totality and
diversity of sources. This was highlighted by
the WA Department of Mines, Industry,
Regulation and Safety (DMIRS) which made
comment that 2023 was the lowest year for
gas exploration in the State of WA for the last
25 years 4.
•
Perth (via the SWIS) set a new all-time
maximum average operational demand
record of 4,046 MW on 23 November 2023
which supersedes the previous high set in
2016 (by 800 MW) and reflects the increase
in electricity demand across the economy.
During peak electricity demand, gas made
up 56% of the total fuel source at around
6:00pm in the evening. The quarter’s cost for
electricity in WA averaged $98.35 MWh
(equivalent to ~$9.83 GJ for gas). This price
was the highest in the nation for the period.
•
During the quarter, the Australian Energy
Market Operator (AEMO) released the WA
Gas Statement of Opportunities 2023
(GSOO 2023). Key points of the report are:
o
The WA domestic gas market is projected
to be in deficit between 2024 and 2029,
with potential supply from committed
and expected projects up to 11 per cent
below forecast demand, and supply >300
TJ/d short from 2030s.
o
WA domestic gas demand is forecast to
increase from 1,066 TJ/day in 2023 to
1,325 TJ/day in 2033 at an annual average
rate of 2.2%.
o
Demand from gas powered generation in
the South West Interconnected System is
forecast to grow from 208 TJ/day in 2023
to a peak of 351 TJ/day in 2032, as
anticipated coal powered generation retirements take place.
Source: WA DMIRS Industry Activity Indicators (https://www.dmp.wa.gov.au/About-Us-Careers/Latest-Resources-Investment-4083.aspx)
4
o
Committed new resources projects, most notably Perdaman’s Karratha Urea Project, are
expected to contribute to a net increase of 132 TJ/day towards gas demand over the
forward period.
•
Subsequent to the release of the GSOO 2023, Alcoa announced that, after a review of the
competitiveness of its 60-year-old Kwinana Alumina refinery, it would cease production in
September 2024. The closure of this plant will reduce daily gas demand from Q4 CY24 by
~55 TJ/d or 3-5% of the total market. The effect on the AEMO forecasts is a reduction from
a market in deficit to one in a delicate balance going in and out of deficit at various times
until 2030.
•
The WA Government’s Economics and Industry Standing Committee Inquiry into the WA
Domestic Gas Policy was expected to release an interim report in late December 2023,
however this has been delayed to early 2024. Commentary to date from the WA Government
has been supportive of building an investment climate for the Perth Basin to arrest any
possible supply deficit through the acceleration of, and increasing the size of, the proposed
developments. This aligns with recent commentary from the Premier, Hon Roger Cook MLA,
reported in The West Australian on January 11, which highlighted that a decision on lifting
WA’s ban on the export of onshore gas is expected by the middle of the year.
•
The WA Government announced that it would spend a further $220 million on subsidising
the coal production from Griffin coal to support the coal fired electricity generation within
the state, but that, in line with its commitment to exit coal fired power by 2029, it would cease
payments to the domestic coal mines in 2026. Strike expects this to stimulate and increase
the immediate investment case for new gas fired generation to be constructed in WA, in
advance of these closures.
Exploration & Development
South Erregulla (L24, STX 100% and operator)
•
The South Erregulla gas field has now been successfully appraised with SE2 & 3 producing
positive results and confirming the continuity of the field to the West and the North.
•
Well testing of SE2 & 3 is planned to occur over the coming quarter which will feed into a
review of the Reserves and Resources within L24.
South Erregulla Exploration & Appraisal Drilling Results
Max Porosity
Average
Porosity
Net Pay
Reservoir
Pressure
Max Rate on
Test
South Erregulla-1
20.2%
13.3%
14m
6,800 psi
80 mmscfd
South Erregulla-2
18%
11%
16m
6,730 psi
TBC
South Erregulla-3
16.4%
10.2%
13m
6,746 psi
TBC
Well
•
The South Erregulla gas field’s Phase 1 development received its primary environmental
approval under Part IV of the Environmental Protection Act 1986 (WA).
•
Strike secured foundation firm gas sales agreements for a total of ~42 PJ which will underpin
the bankability and development of the proposed Phase 1 development. The firm Gas Sales
Agreements are with tier-1 customers and include:
o
A sales agreement for 35.5 PJ (20 TJ/d) of gas to the Worsley Alumina Joint Venture
(operated by South32) for a period of 5 years.
5
o
•
A sales agreement for 5.475 PJ (5 TJ/d) of gas to Perth Energy (AGL) for a period of 3
years.
Further engagement with Enerflex on the modular 40 TJ/d plant continued with a key focus
on cost and schedule optimisation. Strike also engaged with AGIG to provide a
build/own/operate (BOO) solution as part of our competitive tender process for the South
Erregulla export pipeline. This has led to AGIG investigating a bundled gas processing plant
and export pipeline for the treatment and transportation of SE gas production.
West Erregulla (EP469, STX 50% and operator)
•
During the quarter the West Erregulla
upstream
development
Part
IV
environmental
EPA
report
and
recommendation was made public. The
Australian Gas Infrastructure Group
(AGIG)
midstream
87
TJ/d
development
EPA
report
and
recommendation was also made public
during the quarter. Both of these reports
are the subject of appeals with WA
Ministerial determination expected
within the first half of 2024.
•
Strike and Hancock progressed
discussions
around
the
joint
development of the West Erregulla gas
field, with early alignment around
midstream infrastructure and timelines
targeting first gas production by late
2026.
Ocean Hill (EP495, STX 100% and
operator)
•
Through the reporting period, progress
was made securing land access and
approvals for the upcoming ~270 sq km
Ocean Hill 3D seismic campaign, which is
expected to commence in the current
quarter. This high-resolution dataset will be used to site a future appraisal well.
Low Carbon Precinct (100% STX)
•
The South Erregulla-3 well also successfully appraised the Precinct’s CO₂ storage resource
in the Jurassic Sandstones within the Cattamarra Coal Measures. SE3 intersected 75m of
potential storage reservoir with a maximum of 29% porosity and an average of 19%.
•
During the quarter, the Petroleum Amendment Bill 2023 was introduced to the WA
Parliament. The Bill proposes amendments to the Petroleum and Geothermal Energy
Resources Act 1967, the Petroleum Pipelines Act 1969 (PPA) and Petroleum (Submerged
Lands) Act 1982 to, among other things, enable the transport and geological storage of
greenhouse gases and permit the exploration and production of prescribed regulated
substances, such as naturally occurring hydrogen, in WA. The introduction of this Bill supports
6
the work Strike has done to date on proving up its 4.8mt contingent CO2 storage resource 5 in
order to take advantage of potential carbon capture storage opportunities at the Precinct.
•
Strike continued wind data gathering with its LiDAR sensors at the 3,500ha Precinct. During
the quarter the WA Government announced $700 million of funding for transmission
upgrades. Notably $575 million has been allocated to increasing capacity of the network’s
northern section. This will involve upgrading the current mix of 132 kV and 330 kV lines to
unlock the transmission capacity in the Mid-West region.
Financial
•
During the quarter total gross sales from the Walyering gas field were 1.9 PJe of gas and
condensate. This was made up 1.8 PJ of sales gas and 14,601 bbls of associated condensate
across 3 liftings. Average daily production was ~20 TJ/d (being the firm take or pay quantity of
the Santos sales agreement). Nominations above 20 TJ per day were intermittent due to
periods of maintenance on the Parmelia Gas Pipeline. Sales above the 20 TJ/d rate were sold
on an ‘As Available’ basis to both Santos and Alinta Energy.
•
Gross gas sales revenues for the quarter were $13 million ($7.4 million STX share prior to
consolidation of 100% of Walyering). Averaged realised gas prices were ~$7 GJ, slightly lower
due to a softer exchange rate and a higher ‘As Available’ percentage (~5%). Condensate
liftings from Port Bonython totalled $1.4 million and averaged US$83 bbl.
•
Total gross production costs to date have averaged $0.51/GJ. As production rates increase
this is expected to reduce on a per gigajoule basis.
Revenue
Note: Net to Strike is at 55% equity until 31 Dec 2023.
A$ million
Sep Q1
FY24
Dec Q2
FY24
Qtr on Qtr
change
FY23
YTD
FY24
YTD
Change
0.38
13
12.62
0
13.38
13.38
0.21
7.15
6.94
0
7.36
7.36
0
1.4
1.4
0
1.4
1.4
0
0.77
0.77
0
0.77
0.77
0.38
14.39
14.02
0
14.77
14.77
0.21
7.92
7.71
0
8.13
8.13
Sales Revenue
Gas (gross) 6
Gas (net to Strike)
Condensate (gross)
Condensate (net to Strike)
Total Sales Revenue (gross)
Total Sales Revenue (net to Strike)
Average Realised Prices
Gas
($/GJ)
7.34
6.93
(0.41)
-
6.94
6.94
Condensate
($/bbl)
-
101.13
101.13
-
101.13
101.13
Sep Q1
FY24
Dec Q2
FY24
Qtr on Qtr
change
FY23
YTD
FY24
YTD
Change
Exploration & Appraisal
21.37
35
13.64
16.16
56.37
40.2
Development
5.74
1.53
(4.21)
4.87
7.27
2.4
27.11
36.53
9.43
21.03
63.64
42.61
Capital Expenditure
A$ million
Total Capital Expenditure
5 The South Erregulla Contingent CO2 Storage Resource Estimate is set out in ASX announcement dated 15th June 2023 entitled ‘South Erregulla Update’ and is available to view on
Strike Energy's website at www.strikeenergy.com.au. Strike confirms it is not aware of any new information or data that materially affects the information included in the referenced
announcement and that all the material assumptions and technical parameters underpinning the estimate in that announcement continues to apply.
6
Sales gas revenue includes gas banked and not taken or produced pursuant to the ‘Take or Pay’ contract with Santos WA Ltd.
7
Liquidity
Sep Q1
FY24
Dec Q2
FY24
Qtr on Qtr
change
FY23
YTD
FY24
YTD
Change
Cash & Cash Equivalents
103.49
66.78
(36.71)
9.72
66.78
57.06
Undrawn Debt
46.75
46.75
0
6.75
46.75
40
150.24
113.53
(36.71)
16.47
113.53
97.06
A$ million
Total Liquidity
•
During the quarter Strike paid down $6.7 million of drawn debt from its existing Macquarie
Bank facilities. Drawn debt from this facility at the end of the quarter was $19.6 million.
•
Strike finished the quarter with a liquidity position of ~$114 million ($67 million of cash, $47
million of committed, undrawn debt facilities and $0.24 million of listed equities), plus an
uncommitted $80 million contingent debt facility for Strike’s South Erregulla domestic gas
development 7.
•
During the quarter $239,621 in payments were made to related parties for director fees.
Corporate & Commercial
•
During the quarter Strike completed the acquisition of Talon Energy Limited by Scheme of
Arrangement. This transaction has consolidated 100% Strike ownership of the Walyering gas
field in L23 and adjoining exploration acreage in EP447. Post the transaction completing:
o
Strike has commenced a review on the non-operated Talon Energy assets in L7 Mount
Horner and EP437 where the drilling of two wells is expected to occur during 2024.
o
The Condor acquisition agreement expired where Strike exercised its rights to terminate
the agreement with Macallum Energy.
o
Consolidation of the accounts, inclusive of the $6 million facility extended to Talon as part
of the acquisition by Strike, resulted a net -$1.9 million in funds after transaction costs
had been accounted for.
Petroleum Tenements Held at the End of the Quarter
7
Permit
Type
Basin
Play
Operator
(parent)
STX Interest
Gross Area
(acres)
STX Net Area
(acres)
L23 (Walyering)
Production
Perth Basin
Jurassic Wet Gas
Strike
100%
18,222
18,222
L24 (South Erregulla)
Production
Perth Basin
Permian Gas
Strike
100%
18,409
18,409
L7 (Mount Horner)
Production
Perth Basin
Permian Gas/Oil
Triangle
25%
37,021
9,255
EP469 (West Erregulla)
Exploration
Perth Basin
Permian Gas
Strike
50%
55,500
27,750
EP503
Exploration
Perth Basin
Permian Gas
Strike
100%
120,217
120,217
EP504
Exploration
Perth Basin
Permian Gas
Strike
100%
92,170
92,170
EP505
Exploration
Perth Basin
Permian Gas
Strike
100%
18,533
18,533
EP506
Exploration
Perth Basin
Permian Gas
Strike
100%
37,066
37,066
EP447
Exploration
Perth Basin
Jurassic Wet Gas
Strike
100%
127,849
127,849
EP488
Exploration
Perth Basin
Jurassic Wet Gas
Strike
100%
73,390
73,390
Uncommitted facility remains subject to lender credit approval.
8
EP489
Exploration
Perth Basin
Jurassic Wet Gas
Strike
100%
36,572
36,572
EP495
Exploration
Perth Basin
Jurassic Wet Gas
Strike
100%
73,637
73,637
EP437
Exploration
Perth Basin
Permian Gas/Oil
Triangle
25%
176,861
44,215
PPL210 (Aldinga)
Production
Cooper Basin
Shallow Oil
Beach
50%
988
494
PEL 96
Exploration
Cooper Basin
Deep Coal
Strike
67%
668,098
444,953
This report is authorised for release by the Managing Director and Chief Executive Officer in
accordance with the Company’s Continuous Disclosure Policy.
Company Contact
Emma Alexander
Investor Relations & Corporate Manager
Strike Energy Limited
+61 419 877 137
emma.alexander@strikeenergy.com.au
Media Contacts
Paul Ryan
Citadel-MAGNUS
+61 409 296 511
pryan@citadelmagnus.com
Important Notices
Future Statements
Statements contained in this report, including but not limited to those regarding the possible or assumed
future costs, projected timeframes, performance, dividends, returns, revenue, exchange rates, potential
growth of Strike, industry growth, commodity or price forecasts, or other projections and any estimated
company earnings are or may be forward looking statements. Forward looking statements can generally be
identified by the use of words such as ‘project’, ‘foresee’, ‘plan’, ‘expect’, ‘budget’, ‘outlook’, ‘schedule’,
‘estimate’, ‘target’, ‘guidance’ ‘aim’, ‘intend’, ‘anticipate’, ‘believe’, ‘estimate’, ‘may’, ‘should’, ‘will’ or similar
expressions. Forward looking statements including all statements in this document regarding the outcomes
of preliminary and definitive feasibility studies, projections, guidance on future earnings and estimates are
provided as a general guide only and should not be relied upon as an indication or guarantee of future
performance. These statements relate to future events and expectations and as such involve known and
unknown risks and significant uncertainties, many of which are outside the control of Strike. Actual results,
performance, actions and developments of Strike may differ materially from those expressed or implied by
the forward-looking statements in this report. Such forward-looking statements speak only as of the date of
this report. There can be no assurance that actual outcomes will not differ materially from these statements.
A number of important factors could cause actual results or performance to differ materially from the forward
looking statements, including the risk factors set out in Strike West Pty Ltd’s (wholly owned subsidiary of
Strike) bidder’s statement dated 23 December 2022 in relation to its off-market takeover offer to acquire all
of the shares in Warrego Energy Limited that Strike does not already own. Investors should consider the
forward looking statements contained in this report in light of those disclosures. To the maximum extent
permitted by law (including the ASX Listing Rules), Strike and its affiliates and its directors, officers,
employees, agents, associates and advisers disclaim any obligations or undertaking to release any updates
or revisions to the information in this report to reflect any change in expectations or assumptions; do not
make any representation or warranty, express or implied, as to the accuracy, reliability or completeness of the
information in this report, or likelihood of fulfilment of any forward looking statement or any event or results
expressed or implied in any forward-looking statement; and disclaim all responsibility and liability for these
forward-looking statements (including, without limitation, liability for negligence). Nothing in this report will
under any circumstances create an implication that there has been no change in the affairs of Strike since
the date of this report.
9
Quarterly Activities &
Financials
Q2-FY24
Strike’s first full quarter of production operations
Cautionary note and disclaimer
Summary information
This presentation contains summary information and statements about Strike Energy Limited (ASX:STX) (Strike), its subsidiaries and their respective activities, which is current as at the date of this
presentation (unless otherwise indicated).
The information in this presentation is general in nature and does not purport to be exhaustive. For example, this presentation does not purport to contain all of the information that investors may require in
evaluating a possible investment in Strike . It has been prepared by Strike with due care but no representation or warranty, express or implied, is provided by Strike in relation to the currency, accuracy,
reliability, fairness or completeness of the information, opinions or conclusions in this presentation.
This presentation should be read in conjunction with Strike’s other periodic and continuous disclosure announcements lodged with the Australian Securities Exchange (ASX), which are available on the
ASX website (at www.asx.com.au) and the Strike website (at www.strikeenergy.com.au).
No person other than Strike has authorised or caused the issue, release, submission, distribution or provision of this presentation, or takes any responsibility for, or makes or purports to make,
any statements, representations or undertakings in this presentation. Strike, to the maximum extent permitted by law, expressly excludes and disclaims all liability (including, without limitation, any liability
arising out of fault or negligence on the part of any person) for any direct, indirect, consequential or contingent loss or damage, or for any costs or expenses, arising from the use of this presentation or its
contents or otherwise arising in connection with it. Strike does not make any representations or warranties (express or implied) to you about the currency, accuracy, reliability or completeness of the
information, opinions and conclusions in this presentation (including, without limitation, any financial information, any estimates or projections and any other financial information).
Not an offer, and not investment or financial product advice
This presentation is not a prospectus, product disclosure statement or other disclosure document under the Corporations Act, or other offering document under Australian law or any other law. This
presentation has not been lodged with the Australian Securities and Investments Commission. This presentation, and the information contained in it, is provided for information purposes only and is not an
offer or solicitation or an invitation or recommendation to subscribe for, acquire or buy securities of Strike, or any other financial products or securities, in any place or jurisdiction.
This presentation may not be released to US wire services or distributed in the United States. This presentation does not constitute an offer to sell, or the solicitation of an offer to buy, any securities in
the United States or any other jurisdiction in which such an offer would be unlawful. The securities referred to in this document have not been, and will not be, registered under the US Securities Act of 1933
(US Securities Act) and may not be offered or sold in the United States except in transactions exempt from, or not subject to, the registration requirements of the US Securities Act and applicable US
state securities laws.
This presentation, and the information provided in it, does not constitute, and is not intended to constitute, financial product or investment advice (nor tax, accounting or legal advice) or a recommendation
to acquire any securities of Strike. It has been prepared without taking into account the objectives, financial or tax situation or particular needs of any individual. Any investment decision, should be made
based solely upon appropriate due diligence and other inquiries. Before making any investment decision, investors should consider the appropriateness of the information having regard to their own
objectives, financial and tax situation and needs and seek professional advice from their legal, financial, taxation or other independent adviser (having regard to the requirements of all relevant jurisdictions).
Strike is not licensed to provide financial product advice in respect of an investment in securities, and do not purport to give advice of any nature. An investment in any listed company, including Strike, is
subject to risks of loss of income and capital.
Past performance
Past performance metrics and figures, as well as pro forma financial information, included in this presentation are given for illustrative purposes only and should not be relied upon as (and are not) an
indication of Strike’s views on Strike's future financial performance or condition or prospects (including on a consolidated basis). Investors should note that past performance of Strike, including in relation
to the historical trading price of shares, production, reserves and resources, costs and other historical financial information cannot be relied upon as an indicator of (and provide no guidance, assurance or
guarantee as to) future performance, including the future trading price of shares. The historical information included in this presentation is, or is based on, information that has previously been released to
the market.
Investment risk
As noted above, an investment in shares in Strike is subject to investment and other known and unknown risks, some of which are beyond the control of Strike. These risks, together with other general risks
applicable to all investments in listed securities not specifically referred to, may affect the value of shares in Strike in the future. Strike does not guarantee any particular rate of return or the performance of
Strike, nor guarantee the repayment of capital from Strike, or any particular tax treatment. When making any investment decision, investors should make their own enquires and investigations regarding all
information in this presentation, including but not limited to the assumptions, uncertainties and contingencies which may affect future operations of Strike, and the impact that different future outcomes
may have on Strike. Refer to the section 8 of Strike’s Bidder’s Statement dated 23 December 2022 for its off-market takeover offer to acquire all of the shares in Warrego Energy Limited (ACN 125 394
Share your feedback