Supporting Energy Security
South Erregulla is Strike Energy's 100%-owned integrated gas-to-power project, with gas from the South Erregulla field directly fuelling the adjacent 85 MW peaking power station exporting electricity into Western Australia's Wholesale Electricity Market.
The project represents an innovative development pathway for the South Erregulla gas field. Strike is capturing greater value by using the Reserves to fuel a peaking power station, creating a long-life energy asset supported by Capacity Credit revenues and exposure to wholesale electricity prices.
It Offers:
Integrated Energy Development
Combining Strike's wholly owned gas reserves with an 85 MW peaking power station.
Stable Revenue Base
Capacity Credit revenues supplemented by wholesale electricity market sales.
Supports the Energy Transition
Fast-start generation that complements renewable energy and strengthens grid reliability.
Project Overview
Ownership
100% Strike
Status
Commissioning phase
Generation Capacity
85 MW
Infrastructure
Reciprocating engine peaking gas power plant + upstream gathering system
Market
WA primary electricity market via the SWIS
Location
~350 km north of Perth, Perth Basin WA
Asset Status
Mechanical completion achieved and all 20 generating units successfully commissioned on gas from Strike's integrated South Erregulla field. The upstream gas production facility and power station are on standby awaiting connection to the network.
Commercial operations remain subject to completion of commissioning, energisation and network connection activities undertaken with Western Power and AEMO.
About
Located approximately 350 km north of Perth in Production Licence L24, South Erregulla will provide fuel supply for the power station to help meet Western Australia's growing demand for flexible, dispatchable power generation as coal-fired power stations retire.
Infrastructure & Market Access
The South Erregulla Peaking Power Plant (SEPP) comprises 20 × 4.5 MW Jenbacher reciprocating gas engines, an upstream gas gathering and processing facility, approximately 15 km of 132 kV transmission line, and the new Kingia North switchyard. SEPP connects to the grid via the Western Power owned Carey Road Switchyard and a 1.5 km dual-circuit transmission line connecting the project to Western Power's network.
Project Infrastructure
Generation
20 × 4.5 MW Jenbacher reciprocating gas engines
Upstream
Gas gathering and processing facility
Transmission
~15 km of 132 kV transmission line
Switchyard
New Kingia North switchyard
Grid Connection
Western Power owned Carey Road Switchyard
Network Tie-In
1.5 km dual-circuit transmission line
Fuelled by Strike's South Erregulla gas field, the plant has been designed to provide fast-start, flexible generation into WA's SWIS, responding rapidly to periods of peak electricity demand and supporting increasing levels of renewable generation.
Two Complementary Revenue Mechanisms
Reserve Capacity Mechanism
Capacity Credits providing contracted payments for making generation capacity available to the market.
Wholesale Electricity Market
Revenue earned from electricity sales when dispatched during periods of elevated demand and pricing.
This combination provides a stable revenue base through Capacity Credits, while retaining exposure to favourable wholesale electricity market conditions.
Current Activity & Development
In June 2026, the South Erregulla Peaking Power Station achieved mechanical completion. With the commissioning of all 20 units on gas successfully completed, the project has now entered the Western Power commissioning phase. The upstream gas production facility and power station are on standby awaiting connection to the network.
Commissioning Progress
Commissioning • Grid Connection- ✓Mechanical completion achieved, with all major plant and equipment installed and construction activities substantially concluded.
- ✓All 20 generating units successfully commissioned on gas from Strike's integrated South Erregulla field.
- ✓15 km single-circuit overhead powerline connecting the power station to the Western Power connected substation complete.
- ✓All microwave communications infrastructure installed and commissioned.
- ✓Foundations for the 1.5 km dual-circuit overhead transmission line completed.
- •Carey Road substation handed over to Western Power, with network commissioning commencing from July 2026.
- •Upstream gas production facility and power station on standby, under a preservation and care and maintenance program, awaiting connection to the network.
Strike continues to work closely with Western Power and AEMO to progress network commissioning and grid connection activities.
Targeted Online Date
October 2026
Commercial operations remain subject to completion of commissioning, energisation and network connection activities undertaken with Western Power and AEMO.
History
FY22
South Erregulla discovered by Strike within Production Licence L24 in the Perth Basin, and initially assessed as a conventional gas development opportunity.
Appraisal & Certification
Subsequent appraisal drilling and independent reserves certification confirmed a gas resource that required an alternative development pathway. Strike identified the opportunity to maximise value by integrating the field with an 85 MW peaking power station, leveraging the field's gas reserves to generate flexible electricity for Western Australia's Wholesale Electricity Market.
2024
Development of the South Erregulla Peaking Power Plant commenced, with first power targeted for Q4 2026.
March 2026
The 15 km single-circuit overhead powerline connecting the power station to the Western Power connected substation reached 100% completion and dry commissioning activities commenced. The Economic Regulation Authority finalised the Benchmark Reserve Capacity Price for the 2028/29 Capacity Year at $488,500 per MW per annum, a 35% increase on the 2027/28 benchmark, reflecting the increasing value of dispatchable generation as the SWIS transitions away from coal-fired supply.
June 2026
The South Erregulla Power Station achieved mechanical completion, confirming that all major plant and equipment had been installed and construction activities had substantially concluded. South Erregulla gas was successfully introduced into the facility and live commissioning activities commenced.
June 2026
Commissioning of all 20 generating units successfully completed on gas from Strike's integrated South Erregulla field. The project entered the Western Power commissioning phase, with the upstream gas production facility and power station placed on standby awaiting connection to the network.
Q4 2026
First power targeted, delivering 85 MW of firming capacity into the SWIS. Commercial operations remain subject to completion of commissioning, energisation and network connection activities undertaken with Western Power and AEMO.