South Erregulla Update
Released
Released
Announcement PDF
strike@strikeenergy.com.au ABN 59 078 012 745 www.strikeenergy.com.au 1, 40 Kings Park Rd, West Perth WA 6005
South Erregulla Update
• The first Jenbacher engines have arrived onsite and are being installed.
• South Erregulla-1 workover, clean up flow and production simulation has been
completed in readiness for gas supply to the power plant.
• Reports from AEMO indicate the Capacity Price for the 2027/28 Capacity Year will
be at or near the Benchmark Reserve Capacity Price of $360,700/MW per annum,
a 67% increase from the 2026/27 Capacity Year.
Strike Energy Limited (Strike - ASX: STX) is pleased to provide an update on the Company’s
operations and activities at the South Erregulla Peaking Power Plant (“the Project”).
85 MW Peaking Power Plant Construction Progress
The first 12 of 20 engines and alternators for Strike’s 85
MW South Erregulla Peaking Power Plant have now
arrived in Australia and are in the process of being
delivered to site and installed within the engine hall. This
marks a major project milestone and a key step towards
delivering flexible, reliable power to the South West
Interconnected System (SWIS), the primary electricity
grid supplying over one million customers in Western
Australia.
Construction activities remain on schedule, with civil and
electrical works advancing in support of Strike’s target of
first generation by 1 October 2026.
Strike continues to work closely with the Western
Australian Government to optimise transmission
connection timing and costs.
Investors and stakeholders can follow project progress,
milestones, and construction updates via Strike’s
dedicated online project hub at
https://strikeenergy.com.au/on-the-ground-at-south-erregulla.
14th
October 2025 ASX: STX The Company Announcement Officer ASX Ltd via electronic lodgement
2
South Erregulla Workover and Testing
The South Erregulla-1 well has undergone a
workover, clean-up flow and production
simulation program to confirm reservoir
performance and ensure readiness for gas supply
to the power plant.
Importantly, during the simulation period, the well
underwent a three-day production test under
expected operational conditions to calibrate
surface performance data with the balance-of-
plant engineering for the upstream facility.
Capacity Credit Update
Strike’s South Erregulla Peaking Power Plant will
participate in Western Australia’s unique Reserve
Capacity Mechanism (RCM), which plays a vital
role in maintaining reliable electricity supply by
ensuring sufficient generation capacity to meet
peak demand.
Once operational, the facility will earn monthly
Capacity Credit payments, independent of energy
sales, at the Reserve Capacity Price (RCP), providing a stable revenue stream. The RCP is
determined annually, two years in advance, based on a benchmark calculation that is adjusted
to reflect any capacity surplus or deficit in the market, with a “deadband” applying if the market
is within 5% of its target capacity (see Figure 1 on the following page).
Recent Australian Energy Market Operator (AEMO) reports1
on Capacity Credit allocation for the
SWIS indicate that the 2027/28 Capacity Year RCP is expected to be at or near the Benchmark
Reserve Capacity Price of $360,700 per MW per annum, a 67% increase on the 2026/27 RCP of
$216,092 per MW per annum. Subject to AEMO’s final determination, Strike anticipates Capacity
Credit revenue of approximately $30.7 million in year two of operations, before energy sales.
Subject to meeting requirements under the RCM, year one of operations is confirmed to provide
approximately $18.4 million in Capacity Credit revenue. All energy sales will be incremental to
this base Capacity Credit revenue.
Strike will update the market once AEMO confirms the final RCP, expected on or around 27
November 2025. More information about the RCM and Benchmark Reserve Capacity Price is
available under “Fact Sheets” on Strike’s dedicated project hub website.
What’s Next
Strike expects the remaining eight engines to be delivered and installed by year end.
Preparations are also underway for construction of the transmission connection and switchyard
infrastructure, with groundworks scheduled to commence this month.
1
Source: https://www.aemo.com.au/-/media/files/electricity/wem/reserve_capacity_mechanism/certification/2025/certified-reserve-capacity-
assigned-for-the-2027-28-capacity-year.pdf?rev=955e91976a464bd9bfadada3b58d88ae&sc_lang=en
South Erregulla-1 Well Test, October 2025
3
Comments from Managing Director & CEO, Peter Stokes:
“The arrival of the first engines and the work over of South Erregulla-1 represent major
milestones in bringing Strike’s integrated gas-to-power strategy to life.
These achievements demonstrate strong progress towards delivering reliable, flexible energy
to the SWIS, supporting Western Australia’s transition to a cleaner, more resilient power
system.
Furthermore, the significant uplift in the Benchmark Reserve Capacity Price underscores the
importance and necessity of new generation capacity as Western Australia grapples with its
energy transition against a backdrop of rising demand. This is strong validation of Strike’s
strategic positioning, with its material reserves base, ideal location and having the right
projects at the right time in the market.
I look forward to keeping the market updated as South Erregulla progresses towards first
power.”
This announcement is authorised for release by the Managing Director and Chief Executive
Officer in accordance with the Company’s Continuous Disclosure Policy.
Company Contact
Emma Alexander
Investor Relations & Corporate Manager
Strike Energy Limited
+61 419 877 137
emma.alexander@strikeenergy.com.au
Figure 1: Effect of modelled capacity on 2027/28 calculation of final Reserve Capacity Price from
Benchmark Reserve Capacity Price
Forward looking Statements
Statements contained in this release, including but not limited to those regarding the possible or assumed future
costs, projected timeframes, performance, dividends, returns, revenue, exchange rates, potential growth of Strike,
industry growth, commodity or price forecasts, or other projections and any estimated company earnings are or may
be forward looking statements. Forward looking statements can generally be identified by the use of words such as
‘project’, ‘foresee’, ‘plan’, ‘expect’, ‘budget’, ‘outlook’, ‘schedule’, ‘estimate’, ‘target’, ‘guidance’ ‘aim’, ‘intend’, ‘anticipate’,
‘believe’, ‘estimate’, ‘may’, ‘should’, ‘will’ or similar expressions. Forward looking statements including all statements in
this document regarding the outcomes of preliminary and definitive feasibility studies, projections, guidance on
future earnings and estimates are provided as a general guide only and should not be relied upon as an indication or
guarantee of future performance. These statements relate to future events and expectations and as such involve
known and unknown risks and significant uncertainties, many of which are outside the control of Strike. Actual results,
performance, actions and developments of Strike may differ materially from those expressed or implied by the
forward-looking statements in this release. Such forward-looking statements speak only as of the date of this
document. Refer to the risk factors starting on page 31 of the 2025 Annual Report for a summary of certain general
and Strike Energy specific risk factors that may affect Strike Energy. There can be no assurance that actual outcomes
will not differ materially from these statements. Investors should consider the forward looking statements contained
in this release in light of those disclosures. To the maximum extent permitted by law (including the ASX Listing Rules),
Strike and any of its affiliates and their directors, officers, employees, agents, associates and advisers disclaim any
obligations or undertaking to release any updates or revisions to the information in this document to reflect any
change in expectations or assumptions; do not make any representation or warranty, express or implied, as to the
accuracy, reliability or completeness of the information in this document, or likelihood of fulfilment of any forward-
looking statement or any event or results expressed or implied in any forward-looking statement; and disclaim all
responsibility and liability for these forward-looking statements (including, without limitation, liability for negligence).
Nothing in this release will under any circumstances create an implication that there has been no change in the
affairs of Strike since the date of this document.
Share your feedback
Discover