South Erregulla Power Project Update
• 35% increase to the Benchmark Reserve Capacity Price (BRCP) for the 2028/29
Capacity Year determined at $488,500 per MW per annum (2027/28 BRCP:
$360,700 per MW per annum).
• 15 kilometre single circuit overhead power line complete.
• Power station work package nearing completion with electrical contractors to
demobilise from site by the end of March.
• Dry commissioning activities have commenced.
Strike Energy Limited (Strike - ASX: STX) is pleased to provide an update on the South Erregulla
Power Project, which is 100% owned and operated by Strike within L24 in the Perth Basin.
ERA Final Determination for Benchmark Reserve Capacity Price
The Western Australian Economic Regulation Authority (ERA) has finalised its Determination for
the Benchmark Reserve Capacity Price (BRCP) for the 2028/29 Capacity Year at $488,500 per
MW per annum.
The final BRCP for 2028/29 represents a 35% increase on the 2027/28 benchmark of
$360,700/MW/year, reflecting updated assessments of new-entrant costs and the increasing
value of dispatchable generation as the SWIS transitions away from coal-fired supply.
The BRCP forms a benchmark input to the Reserve Capacity Mechanism (RCM) within the
Wholesale Electricity Market. Actual capacity payments are determined yearly through the
RCM based on the interaction between the Reserve Capacity Requirement (RCR) set by
AEMO and the volume of certified capacity offered by market participants. Where certified
capacity exceeds the RCR, clearing prices may be below the BRCP; where capacity is in deficit
relative to the RCR, prices may clear at or above the BRCP.
The final BRCP determination strengthens the benchmark economics underpinning new
entrant firming generation in the SWIS and supports the long-term revenue framework for
projects such as South Erregulla.
South Erregulla Capacity Position
The South Erregulla Power Plant is already accredited within the RCM on a variable basis
and has been awarded 85 MW of certified capacity for the 2026/27 and 2027/28 capacity
years. Subject to meeting performance and testing requirements under the Wholesale
Electricity Market (WEM) Rules, these capacity credits equate to:
o 2026/27 Capacity Year ($216,092/MW/yr) = $18.4m
o 2027/28 Capacity Year ($360,700/MW/yr) = $30.7m
Strike expects to be awarded its full 85 MW of capacity for the 2028/29 capacity year,
subject to the normal certification processes under the WEM Rules.
While capacity allocation is expected to remain stable, the capacity price applicable to
2028/29 will depend on the broader SWIS supply–demand balance determined in
November 2026.
ASX: STX The Company Announcement Officer ASX Ltd via electronic lodgement
16th
March 2026
Operational Update: South Erregulla Peaking Power Plant
Construction of the 85 MW South Erregulla Peaking Power Station continues to progress well,
with the project remaining on budget and on schedule for targeted completion by 1 October
2026. Overall, the project is now 82% complete, with procurement at 96% complete.
Key progress achieved during the current construction phase includes:
The 15 km single circuit overhead powerline that connects the power station to the
Western Power connected substation is now 100% complete.
The power station work package is nearing completion with electrical contractors
preparing to demobilise from site by the end of March.
Dry commissioning activities have commenced.
The upstream gas gathering system construction is advancing with first gas expected
into the system in early Q2 CY 2026.
Strike continues to work closely with its construction contractors and Western Power to ensure
the project remains on track to deliver firming capacity into the SWIS by 1 October 2026.
Once operational, the South Erregulla Power Plant will provide fast-start, flexible gas-fired power
generation, supporting system reliability and renewable integration within Western Australia’s
evolving electricity market.
Power Station Package and 15 km Overhead Power Line
Termination wiring at the Power Station Inlet Gas Valves
Pre-Commissioning Generator Energisation
This announcement is authorised for release by the Chief Executive Officer and Managing
Director in accordance with the Company’s Continuous Disclosure Policy.
Company Contact
Emma Alexander
Investor Relations & Corporate Manager
Strike Energy Limited
+61419877137
emma.alexander@strikeenergy.com.au
Important Notices
Forward looking Statements
Statements contained in this release, including but not limited to those regarding the possible or assumed
future costs, projected timeframes, performance, dividends, returns, revenue, exchange rates, potential
growth of Strike, industry growth, commodity or price forecasts, or other projections and any estimated
company earnings are or may be forward looking statements. Forward looking statements can generally
be identified by the use of words such as ‘project’, ‘foresee’, ‘plan’, ‘expect’, ‘budget’, ‘outlook’, ‘schedule’,
‘estimate’, ‘target’, ‘guidance’ ‘aim’, ‘intend’, ‘anticipate’, ‘believe’, ‘estimate’, ‘may’, ‘should’, ‘will’ or similar
expressions. Forward looking statements including all statements in this document regarding the
outcomes of preliminary and definitive feasibility studies, projections, guidance on future earnings and
estimates are provided as a general guide only and should not be relied upon as an indication or guarantee
of future performance. These statements relate to future events and expectations and as such involve
known and unknown risks and significant uncertainties, many of which are outside the control of Strike.
Actual results, performance, actions and developments of Strike may differ materially from those
expressed or implied by the forward-looking statements in this release. Such forward-looking statements
speak only as of the date of this document. Refer to the risk factors starting on page 31 of the 2025 Annual
Report for a summary of certain general and Strike Energy specific risk factors that may affect Strike
Energy. There can be no assurance that actual outcomes will not differ materially from these statements.
Investors should consider the forward looking statements contained in this release in light of those
disclosures. To the maximum extent permitted by law (including the ASX Listing Rules), Strike and any of
its affiliates and their directors, officers, employees, agents, associates and advisers disclaim any
obligations or undertaking to release any updates or revisions to the information in this document to
reflect any change in expectations or assumptions; do not make any representation or warranty, express
or implied, as to the accuracy, reliability or completeness of the information in this document, or likelihood
of fulfilment of any forward-looking statement or any event or results expressed or implied in any forward-
looking statement; and disclaim all responsibility and liability for these forward-looking statements
(including, without limitation, liability for negligence). Nothing in this release will under any circumstances
create an implication that there has been no change in the affairs of Strike since the date of this
document.
Share your feedback
Discover