Walyering West Drilling Commenced
strike@strikeenergy.com.au ABN 59 078 012 745 www.strikeenergy.com.au 1, 40 Kings Park Rd, West Perth WA 6005
Walyering West Drilling Commenced
• Drilling operations at Walyering West-1 have commenced with the Ensign 970
rig.
• Drilling ahead at 1,006m MDRT (measured depth).
Strike Energy Limited (Strike - ASX: STX) is pleased to provide an update on the near-field
exploration drilling operations at Walyering West-1 (WAW-1) within L23 in the Perth Basin. Strike
Energy Limited is operator and the holder of 100% equity in L23.
WAW-1 is a near-field exploration well located approximately 3 km from existing production
infrastructure at the Walyering Gas Plant and is targeting sandstone reservoirs within the
Cattamarra Coal Measures (CCM) formation, with the objective of evaluating gas and
condensate potential within a proven hydrocarbon system.
Comments from Strike’s CEO & MD, Peter Stokes:
“Commencement of drilling at Walyering West-1 represents an excellent opportunity to unlock
additional value from our Walyering asset.
As a near-field exploration prospect, success at this well has the potential to be rapidly
commercialised through existing infrastructure, supporting efficient production growth and
capital discipline.
Importantly, success would provide upside to our base business, further enhancing our
production and development outlook.”
Current Operations
Rig maintenance and rig move operations were completed on schedule and without incident.
Strike officially spud WAW-1 at 11:30 on Wednesday the 15th
of April 2026. Drilling operations
have commenced with the well drilling ahead at a depth of 1,006m MDRT.
Forward Plan
Strike will drill ahead to the first casing point at an approximate depth of 2,624m MDRT before
running and cementing 9-5/8” casing in place. An 8-1/2” hole will be drilled to an approximate
Total Depth of 3,639 m MDRT before running wireline logging and, on success, 7” casing to
enable well testing.
Drilling operations are expected to take approximately 20 days, with preliminary results
anticipated in early May. Further evaluation, including wireline logging and potential production
testing, will be undertaken as part of the program.
Strike will update the market as material results become available.
About the Walyering West-1 Campaign
The Walyering West-1 well is located at Lat: 30° 43' 40.00" S, Long: 115° 27' 00.52" E. The well is
targeting Jurassic aged conventional sandstone reservoirs within a fault bound, 4-way dip
closure.
ASX: STX The Company Announcement Officer ASX Ltd via electronic lodgement
16th
April 2026
The Walyering West-1 well will be drilled down to a depth of 3,639 m MDRT and is designed to
test Prospective Resource of 46 PJ1
within the A to D Sands of the Cattamarra Formation. On
success, Walyering West-1 will be tied into the Walyering Gas Processing Facility located
approximately 3 kilometers to the northeast.
Prospective Resource
Estimate Information &
Cautionary statement: The
above estimated quantities of
petroleum that may potentially
be recovered by the
application of a future
exploration and development
project(s) relate to
undiscovered accumulations.
These estimates are un-risked,
probabilistically determined,
and have both an associated
chance of discovery of 26%
and a chance of development
estimated to be 90%. Further
exploration, appraisal and
evaluation is required via
drilling and testing to
determine the existence of a
significant quantity of
potentially moveable
hydrocarbons.
This announcement is authorised for release by the Managing Director and Chief Executive
Officer in accordance with the Company’s Continuous Disclosure Policy.
Company Contact
Emma Alexander
Investor Relations & Corporate Manager
Strike Energy Limited
+61419877137
emma.alexander@strikeenergy.com.au
Important Notices
Forward looking Statements
Statements contained in this release, including but not limited to those regarding the possible or assumed
future costs, projected timeframes, performance, dividends, returns, revenue, exchange rates, potential
growth of Strike, industry growth, commodity or price forecasts, or other projections and any estimated
1
Refer to ASX announcement on 19 August 2025 entitled “Walyering Reserves & Resources Update and Resulting Impairment” for more information.
Strike is unaware of any new information that materially impacts the information in the release and confirms that all the material assumptions and
technical parameters underpinning the estimate continue to apply and have not materially changed.
company earnings are or may be forward looking statements. Forward looking statements can generally
be identified by the use of words such as ‘project’, ‘foresee’, ‘plan’, ‘expect’, ‘budget’, ‘outlook’, ‘schedule’,
‘estimate’, ‘target’, ‘guidance’ ‘aim’, ‘intend’, ‘anticipate’, ‘believe’, ‘estimate’, ‘may’, ‘should’, ‘will’ or similar
expressions. Forward looking statements including all statements in this document regarding the
outcomes of preliminary and definitive feasibility studies, projections, guidance on future earnings and
estimates are provided as a general guide only and should not be relied upon as an indication or guarantee
of future performance. These statements relate to future events and expectations and as such involve
known and unknown risks and significant uncertainties, many of which are outside the control of Strike.
Actual results, performance, actions and developments of Strike may differ materially from those
expressed or implied by the forward-looking statements in this release. Such forward-looking statements
speak only as of the date of this document. Refer to the risk factors starting on page 31 of the 2025 Annual
Report for a summary of certain general and Strike Energy specific risk factors that may affect Strike
Energy. There can be no assurance that actual outcomes will not differ materially from these statements.
Investors should consider the forward looking statements contained in this release in light of those
disclosures. To the maximum extent permitted by law (including the ASX Listing Rules), Strike and any of
its affiliates and their directors, officers, employees, agents, associates and advisers disclaim any
obligations or undertaking to release any updates or revisions to the information in this document to
reflect any change in expectations or assumptions; do not make any representation or warranty, express
or implied, as to the accuracy, reliability or completeness of the information in this document, or likelihood
of fulfilment of any forward-looking statement or any event or results expressed or implied in any forward-
looking statement; and disclaim all responsibility and liability for these forward-looking statements
(including, without limitation, liability for negligence). Nothing in this release will under any circumstances
create an implication that there has been no change in the affairs of Strike since the date of this
document.
Share your feedback
Discover