Credit approval for $162 million development facility
Released
Released
Announcement PDF
30th January 2025
ASX: STX The Company Announcement Officer ASX Ltd via electronic lodgement
Credit approval for $162 million
development facility
•
Credit approval received from Macquarie for $162 million of committed funding of
the $217 million total financing package.
•
Committed funds will be primarily used to refinance existing debt and to fund the
development of the Company’s South Erregulla Power Project.
Strike Energy Limited (Strike - ASX: STX) is pleased to announce that it has received credit
approval from Macquarie Bank Limited (“Macquarie”) for an initial $162 million of committed
funding. Further tranches of the previously announced $217 million total funding package will
be subject to Macquarie credit approval as and when the need for access to the funds is
required.
The financing package provides attractive long-term funding to support execution of the
Company’s Perth Basin gas and power generation developments.
The initial $162 million committed financing package includes two facilities:
•
$113 million term debt financing facility to refinance the existing debt, for capitalisation
of interest, to fund development of the Company’s South Erregulla Power Project and
provide general working capital; and
•
$49 million asset financing facility for procurement of the reciprocating gas engines that
will be installed at the South Erregulla Power Project.
Of the balance of the $217 million total funding package that remains subject to Macquarie
credit approval, a further $15 million in asset financing will be used to fund South Erregulla
procurement packages and a $40 million term debt facility will be used to fund the development
of the West Erregulla gas field. Credit approval will be sought at the appropriate time.
Strike and Macquarie will move to finalise and execute the definitive financing documentation
that is already well progressed.
The key terms of the facilities are set out at the end of this release and will be provided subject
to draw down conditions and financial, corporate and project related covenants customary for
these types of arrangements. The existing security package granted to Macquarie in respect to
the current facility will remain in place as security for the refinanced package expanded to
include the assets to which the asset finance relates.
This announcement is authorised by Jill Hoffmann, Acting Chief Executive Officer of Strike in
accordance with the Company’s Continuous Disclosure Policy.
Company Contact
Emma Alexander
Investor Relations & Corporate Manager
Strike Energy Ltd
+61 419 877 137
emma.alexander@strikeenergy.com.au
strike@strikeenergy.com.au
ABN 59 078 012 745
Media Contacts
Paul Ryan
Senior Director
Sodali & Co.
+61 409 296 511
paul.ryan@sodali.com
www.strikeenergy.com.au
1, 40 Kings Park Rd, West Perth WA 6005
$217 million Financing Package Key Terms
Key Terms
Debt Facility
Total Facility
$153 million
Tranches
Tranche A: $73 million (committed)
Tranche B: $40 million (committed)
Tranche C: $40 million (uncommitted)
Tenor
48 months
Maturity date
March 2029
Interest rate
BBSY + 6%
Amortisation commencement
December 2026
Balloon repayment
$88 million
Key Terms
Asset Finance Facility
Total Facility
$64 million
Tranches
Tranche A: $49 million (committed)
Tranche B: $15 million (uncommitted)
Tenor
78 months
Maturity date
September 2031
Interest rate
BBSY + 7.6% (Escrow period during construction)
BBSY + 6% (5 year finance lease period)
Lease payment commencement
October 2026
Balloon repayment
$39 million