Highlights
South Erregulla Power Plant (SEPP) planned grid energisation on 20 November 2026 in conjunction with Western
Power
Grid connection and energisation to be followed by AEMO hold-point testing over a six to eight week period
Importantly, revenue generation can commence during the AEMO process, with a gradual ramp up in approved
production levels through this certification process enabling increased electricity sales and cashflow
Capacity credit payments commence at the conclusion of AEMO testing when an interim authority to generate is
issued. Capacity prices are locked-in two years ahead providing a fixed revenue stream, independent of electricity
sales
Contracted revenue for Capacity Years (CY; 1 October to 30 September) CY27 is ~$12m (pro-rata assuming January
2027 commencement), $31m in CY28 and $39m in CY29 with electricity sales providing additional upside
An illustrative scenario for Capacity Year 29 indicates capacity revenue of $39m and electricity sales of ~$36m1
representing $25/GJ on a look-through basis
Low operating costs (driven by raw gas direct from wellhead) provide strong EBITDA margin
Strike Energy Limited (ASX: STX) is pleased to provide an update on the grid connection and energisation of the 85
MW South Erregulla Power Plant (SEPP), located adjacent to the Company's 100 per cent owned South Erregulla
gas field in Western Australia.
SEPP has now entered the final stages of facility commissioning, with the much-anticipated milestone of grid
energisation scheduled for 20 November 2026 in conjunction with Western Power.
Following energisation, AEMO hold-point testing activities are expected to commence immediately and forecast
to take approximately six to eight weeks. Revenue generation commences from the start of the AEMO hold-point
testing program, with a ramp-up in production through this certification process, providing the opportunity to
accelerate first cash generation. Subject to successful completion of hold-point testing, full commercial operations
will commence.
1 Assuming plant operated at 10 hours per day at an average electricity price of ~$110/MWh. Illustrative only and not a forecast. Actual revenue will vary
with dispatch, realised electricity prices, plant availability and operating conditions. Capacity year is from 1 October to 30 September.
ASX: STX The Company Announcement Officer ASX Ltd via electronic lodgement
Strike Energy | ASX:STX 2
The commencement of commercial operations will mark a significant milestone for Strike as the Company
transitions from project development into ownership and operation of critical energy infrastructure with dual
revenue streams from both Capacity Credits and electricity sales.
Capacity Credit Revenue Foundation
A key feature of the South Erregulla Power Plant is the revenue generated through Western Australia's Reserve
Capacity Mechanism, under which Capacity Credits are awarded ahead of each capacity year.
SEPP has already secured Capacity Credits for its full 85 MW capacity, providing a fixed earnings base that is
independent of dispatch volumes and wholesale energy prices.
The project's contracted capacity revenues underpin infrastructure-style cash flows and establish a strong earnings
foundation upon commencement of operations, while electricity sales provide additional earnings upside during
periods of elevated demand and power prices.
Capacity Credits, both quantity and price, are fixed for SEPP on a rolling two-year lookahead basis, enhancing
earnings certainty and supporting long-term cash flow generation.
The project is expected to generate contracted capacity revenues of approximately $12m in CY27 to 30 September
2027, $31m in CY28 and $39m in CY29, with payments received weekly. These revenues are fixed under the
Reserve Capacity Mechanism.
Managing Director and CEO, Shelley Robertson commented:
"South Erregulla is now entering the final stages of facility commissioning, with energisation scheduled for 20
November.
The project is progressing toward commercial operations, which will establish two new earning streams for Strike
through contracted Capacity Credit revenue and electricity sales into the Western Australian market. Capacity
Credit revenues have already been secured under Western Australia’s Reserve Capacity Mechanism, providing us
with a fixed earnings foundation on a two-year rolling forecast.
South Erregulla represents the successful execution of our strategy to enhance the value of our gas resources
through downstream energy infrastructure, creating a long-life asset capable of generating visible and recurring
cash flows while supporting Western Australia’s demand for reliable and flexible power generation."
This announcement has been authorised for release by the Managing Director and Chief Executive Officer in
accordance with the Company’s Continuous Disclosure Policy.
Further information
Shelley Robertson
Managing Director & Chief Executive Officer
Strike Energy Limited
shelley.robertson@strikeenergy.com.au
Strike Energy | ASX:STX 3
Follow us on
To learn more, visit
www.strikeenergy.com.au
About Strike Energy
Strike Energy Limited (ASX:STX) is a leading independent energy company delivering reliable domestic gas and developing flexible power generation for
Western Australia. Strategically located near key processing and transmission infrastructure in the Mid West, Strike is building a diversified portfolio of gas
production, power generation and exploration assets. Strike has one of the largest discovered gas portfolios in the onshore Perth Basin and Mid West,
including the expansive Greater Erregulla Permian fields and condensate rich Walyering Jurassic field.
FORWARD LOOKING STATEMENTS
Statements contained in this release, including but not limited to those regarding the possible or assumed future costs, projected timeframes, performance,
dividends, returns, revenue, exchange rates, potential growth of Strike, industry growth, commodity or price forecasts, or other projections and any
estimated company earnings are or may be forward looking statements. Forward looking statements can generally be identified by the use of words such
as ‘project’, ‘foresee’, ‘plan’, ‘expect’, ‘budget’, ‘outlook’, ‘schedule’, ‘estimate’, ‘target’, ‘guidance’, ‘aim’, ‘intend’, ‘anticipate’, ‘believe’, ‘estimate’, ‘may’,
‘should’, ‘will’ or similar expressions. Forward looking statements including all statements in this document regarding the outcomes of preliminary and
definitive feasibility studies, projections, guidance on future earnings and estimates are provided as a general guide only and should not be relied upon as
an indication or guarantee of future performance. These statements relate to future events and expectations and as such involve known and unknown risks
and significant uncertainties, many of which are outside the control of Strike. Actual results, performance, actions and developments of Strike may differ
materially from those expressed or implied by the forward-looking statements in this release. Such forward-looking statements speak only as of the date
of this document. Refer to the risk factors starting on page 30 of the 2026 Annual Report for a summary of certain general and Strike Energy specific risk
factors that may affect Strike Energy. There can be no assurance that actual outcomes will not differ materially from these statements. Investors should
consider the forward looking statements contained in this release in light of those disclosures. To the maximum extent permitted by law (including the ASX
Listing Rules), Strike and any of its affiliates and their directors, officers, employees, agents, associates and advisers disclaim any obligations or undertaking
to release any updates or revisions to the information in this document to reflect any change in expectations or assumptions; do not make any
representation or warranty, express or implied, as to the accuracy, reliability or completeness of the information in this document, or likelihood of fulfilment
of any forward-looking statement or any event or results expressed or implied in any forward-looking statement; and disclaim all responsibility and liability
for these forward-looking statements (including, without limitation, liability for negligence). Nothing in this release will under any circumstances create an
implication that there has been no change in the affairs of Strike since the date of this document.
Share your feedback
Discover