Q4 FY24 Quarterly Report & Appendix 5B
Released
Released
Announcement PDF
Q4 FY24 Quarterly Report
25th July 2024
Walyering 7 co-located with the Walyering Gas Plant
Comments from Managing Director & CEO, Stuart Nicholls:
“Strike has finished a productive quarter which included record production and revenue
at Walyering, the receipt of major environmental approvals for the West Erregulla gas
project and the submission of an application to AEMO for the development of a fully
integrated 85 MW peaking gas power station at South Erregulla, built on the Precinct.
Strike continued to demonstrate the upside in its substantial, ~3,500km² Perth Basin
position, with a gas and condensate discovery at the Walyering-7 well, the spud of the
Erregulla Deep-1 well, completion of the Kadathinni 2D seismic and the receipt of the
first data volumes of the exciting Ocean Hill 3D seismic.
The business is now focussed on preparing for key milestones in its Gas Acceleration
Strategy, including final investment decisions for the West Erregulla field development
and the South Erregulla power project.”
Highlights
Walyering
•
Walyering quarterly gas and condensate sales volumes increased by 7% to ~2.4 PJe with sales
revenues increasing by 13% to approximately $20 million.
•
Walyering-7 drilling and testing has confirmed the presence of a conventional gas and
condensate accumulation with 23m of net pay.
South Erregulla
•
Strike submitted a proposal to the AEMO to build a fully integrated 85 MW Peaking Power
Plant on the Precinct to maximise the value of the South Erregulla resource base 1.
•
Reserves and resources of 82 PJ 2P plus 2C were re-certified by Netherland, Sewell &
Associates Inc. (NSAI) 2.
1 Refer to Important Notices at the end of this report. For more information, see ASX announcement dated 24 June 2024 entitled “South Erregulla Peaking Power Plant submission supported by SE Reserves”.
2 Refer to Important Notices at the end of this report for important information on Reserves and Resources estimations.
Strike Energy Limited ABN 59 078 012 745
www.strikeenergy.com.au
P: +61 8 7099 7400
E: strike@strikeenergy.com.au
Level 1, 40 Kings Park Road
West Perth WA 6005
West Erregulla
•
Received Part IV primary environmental approvals for the upstream and midstream
infrastructure for the proposed 87 TJ/d West Erregulla gas field development 3.
•
The CSBP firm gas supply agreement from West Erregulla has expired and now reverts to the
original option for gas supply under the Gas Sales Option Agreement announced in May 2019.
Exploration & Appraisal
•
The Erregulla Deep-1 well in EP469 spudded during the quarter and has reached a depth of
3709m MD.
•
The 484 km Kadathinni 2D seismic campaign was completed on time and on budget.
•
Rig slot allocated for the drilling of the prospective Walyering East structure in late 2024,
4.5km to the north-east of the Walyering processing facility.
Corporate
•
Terms agreed with Macquarie Bank for the provision of a 5-year, $153 million financing
package 4 for its Perth Basin Gas Acceleration Strategy.
•
Minimum holding buy-back completed, reducing the Company’s total number of
shareholders by 8%.
Key Performance Metrics
Mar Q3
FY24
Jun Q4
FY24
Qtr on Qtr
change
FY23
YTD
FY24
YTD
Change
(PJe net)
2.2
2.4
7%
-
6.5
-
(PJe net)
2.2
2.4
7%
-
5.6
-
17.6
19.9
13%
-
52.2
-
17.6
19.9
13%
-
45.6
-
Cash and cash equivalents
44.6
38.8
(13%)
129
38.8
(70%)
Undrawn debt
46.8
46.8
-
46.8
46.8
-
Total Liquidity
91.4
85.5
(6%)
175.8
85.5
(51%)
Mar Q3
FY24
Jun Q4
FY24
Qtr on Qtr
change
FY23
YTD
FY24
YTD
Change
PJ
2.2
2.3
4%
-
6.3
-
PJ
2.2
2.3
4%
-
5.5
-
kbbl
17.1
17
0%
-
49
-
kbbl
17.1
17
0%
-
42.3
-
PJe
2.3
2.4
4%
-
6.6
-
PJe
2.3
2.4
4%
-
5.7
-
MMboe
0.4
0.4
4%
-
1.1
-
MMboe
0.4
0.4
4%
-
0.9
-
A$ million unless indicated
Sales volume (gross)
Sales volume (net to Strike)
Sales revenue (gross)
Sales revenue (net to Strike)
Production
Production by product
Sales gas (gross) 5
Sales gas (net to strike)
Condensate (gross)
Condensate (net to strike)
Total production (gross)
Total production (net to Strike)
Total production (gross)
Total production (net to Strike)
Note: Net to Strike is 55% equity to 31 Dec 2023 and 100% thereafter.
3 For more information, see ASX announcement dated 9 July 2024 entitled “West Erregulla receives EPA Approval”.
4 For more information, see ASX announcement dated 21 June 2024 entitled “Terms agreed for $153m Development Funding Package”.
5 Sales gas production includes gas invoiced in a prior period and taken as ‘banked gas’ pursuant to the ‘Take or Pay’ contract with Santos WA Ltd.
2
Walyering (L23, 100% and operator)
•
The Walyering gas field produced a
total of ~2.4 PJe of gas and condensate
for the quarter or approximately 25 TJ/d
of sales gas and 185 bbls/d of
condensate.
•
Walyering-7 (W-7) was drilled and
commenced testing during the quarter
which confirmed the presence of a
conventional gas and condensate
accumulation with 23m of net pay in
the primary objectives within the
Cattamarra Formation. The well has
been tested into the facility where all
gas and condensate from the test has
been sold into Strike’s existing
marketing arrangements.
Whilst
testing is ongoing Strike has observed
the A-Sands as having a higher
condensate gas ratio and heating value
than expected which whilst preliminary
is a positive development. At the
conclusion of the testing, Strike
intends for W-7 to be permanently tied
into the facility, which is expected to
occur by the end of the coming quarter.
•
Given the higher condensate yields
observed during the first stage of
testing at W-7, Strike is investigating possible localised sales and use opportunities for the
condensate. Strike has completed a more than 1,000-hour test program fuelling a gasoline
generator and generating power with the condensate as it looks broadly across all possible
alternative commercialisation pathways.
•
Walyering-6 (W-6) conducted flow testing of a new previously untested zone in the upper
Cattamarra Formation, which was identified on a post startup petrophysical review. Positively,
sustained gas production of 5 TJ/d, with a manageable yet variable water cut depending on
gas rates, was initiated from a 5m sand. This zone is in addition to the existing producing
reservoirs in the Cadda and Cattamarra Formations.
•
RISC Advisory Pty Ltd commenced its process for reviewing the Walyering Reserves and
Resources. This review will include the production from Walyering, the new zone tested at W6 and the results of the drilling and testing at W-7. This review is expected to be complete by
the end of August 2024.
•
Strike has allocated a rig slot in December 2024 to drilling the prospective Walyering East
structure, 4.5 km to the north-east of the Walyering gas processing facility and defined on the
existing 3D seismic. Whilst Ocean Hill remains the priority for rig allocation, Ocean Hill-2 will
not be ready to appraise until early 2025 due to processing timelines of the recently acquired
3D seismic. Drilling of the Walyering East well is also timely with the PGP to DBNGP crossing
at Mondarra estimated to become available in December 2024 which will broaden
Walyering’s gas marketing opportunities.
3
WA Energy Market
•
WA gas market conditions have softened from
historical highs as large suppliers return to the
market offering new short term gas contracts,
however, spot prices continue to remain at
elevated levels in the high $8 per gigajoule range.
•
The market remained resilient despite extended
outages in June with KGP ullage and sustained
storage withdrawals (Mondarra & Tubridgi) filling
any immediate supply gaps. Of the last 14 quarters
storage volumes across WA have only been
replenished on 3 occasions, demonstrating the
long-term changes in the gas market dynamic.
•
The Economic Standing
Committee resolved to
postpone the tabling of the
final report on its inquiry
into the WA Domestic Gas
Policy. The committee will
now table the report on
Thursday 15 August 2024.
Strike continues to engage
with the WA Government
on the merits of allowing
some exports from the
Perth Basin to maximise
and accelerate exploration
and
production
of
domestic gas.
•
Electricity markets continue to be a major driver of gas demand and pricing dynamics with
gas contributing ~42% to operational electricity demand during the quarter.
•
The quarter’s average cost
for electricity in WA was
$80.30/MWh, with average
peak energy prices (4pm –
9pm) of $169/MWh.
•
Trading intervals of max
pricing ($738/MWh or ~$92
GJ equivalent using 8 GJ
per MW) continue to occur
frequently in the WA
Wholesale
Electricity
Market with a total of 124
Reference Trading Price
intervals
(30-minutes)
reaching the capped price
for the quarter.
4
Exploration & Development
West Erregulla (EP469, STX 50% and operator)
•
During the quarter Strike (on behalf of the
EP469 Joint Venture) was awarded the
West Erregulla upstream development Part
IV environmental EPA approval, as was
Australian Gas Infrastructure Group
(AGIG), as the operator of the proposed
midstream development. These approvals,
which took ~3 years, are a major derisking
event for the project.
•
The CSBP firm gas supply agreement
expired during the quarter and reverted to
the original option for gas supply under the
Gas Sales Option Agreement announced
on 29 May 2019. As a result, the fixed gas
price that had been agreed under the firm
gas supply agreement will revert to the
option price as calculated under the Gas
Sales Option Agreement (up to 25 TJ/d and
a total contract quantity of 100 PJ).
•
Strike progressed the development and gas
processing agreements with AGIG for the
construction and tolled gas processing
services for the proposed 87 TJ/d gas plant
and pipeline connection into the DBNGP.
•
Work on the Field Development Plan for the
proposed 87 TJ/d development was
conducted and is undergoing further joint
venture review.
•
Strike progressed the Production Licence
application and has accepted the draft instrument expecting the formal grant from DEMIRS
shortly.
•
Strike spudded the Erregulla Deep-1 exploration well, which is currently at 3,709m Measured
Depth and is drilling ahead. Unfortunately, eleven days of downtime has been incurred due
to unforeseen repairs related to the drilling rig. All downtime costs related to this issue were
at the drilling contractor’s expense.
South Erregulla (L24, STX 100% and operator)
•
During the quarter, Strike submitted an application to the Australian Electricity Market
Operator (AEMO) for the award of capacity credits and network access to support a standalone development proposal at South Erregulla. The submission was for Strike to construct
and operate a fully integrated 85 MW peaking gas power plant on Strike’s Precinct with
operations to commence by October 2026.
5
•
The proposed power plant
will be fuelled by South
Erregulla’s re-certified gas
Reserves, where the 1P
Reserves
of
37
PJ 6
supports a project life of
more than 25 years 7.
•
Strike expects to be
informed in August 2024
as to whether it has been
awarded
capacity
by
AEMO. In October, Strike
will be informed of the
price of that capacity, as
well as network access
quantity awarded to it. This
will lead into Strike being able to contemplate a
Final Investment Decision (FID) in November
2024.
•
This strategic development plan for South
Erregulla capitalises on the:
o
incremental value that integrated gas-topower projects can generate from the
spark-spread during short term power
prices coinciding with lower renewable
generation;
o
capacity credit mechanism now in force in
WA, whereby payments from the WA
Government provide Strike with a high
degree of confidence in the return profile of
the project;
o
Assumes ~8 GJ/MW produced with a base assumption of
geographical competitive advantage Strike
$8 GJ for domestic gas, using Walyering sales as a benchmark.
has over the traditional WA domestic gas
market (Carnarvon Basin) incumbents and other non-integrated generators; and
o
Strike’s existing approvals and much of the planning work completed in contemplation
of the previous South Erregulla domestic gas project.
•
The capital cost estimate for the power project has been compiled by Strike and its
engineering consultants to a AACE Class 3 Estimate Classification (-15% to +30%) level of
accuracy. Estimated capital costs, at this stage in the project’s development cycle, range
between $120 million and $160 million.
•
As disclosed on the 21st of June 2024, Strike has agreed terms for a financing package from
Macquarie Bank. Of this package, $53 million is allocated to the South Erregulla power project
development, which when combined with strong free cashflow generation from Strike’s
existing production operations, allows for Strike to meet the modelled mid-case capital
requirements for the project’s development and construction.
6 Reserves re-certified by NSAI as at 31 May 2024 and reported to Strike on 21 June 2024. Refer to ASX announcement “South Erregulla Reserves” dated 24 June 2024 for important
information regarding the South Erregulla Reserves and Resources report and to the Important Notices at the end of this release.
7 Project life modelled on average throughput of ~1.3 PJ per annum, refer ASX announcement dated 24 June 2024 entitled “South Erregulla Peaking Power Plant submission supported
by SE Reserves” for key operating assumptions.
6
Ocean Hill
(EP495, STX 100% and operator)
•
Strike has received fast-track processing of
the recently acquired Ocean Hill 3D
dataset by RealTime Seismic with a
significant uplift in data quality compared
to the original 2D seismic survey.
•
Positively, preliminary interpretation of the
data suggests a simpler structure with
fewer large-scale, continuous faults leading
to lower interpreted compartmentalisation
across the Ocean Hill gas discovery.
•
Seismic reflectivity within the Cattamarra
Formation is interpreted to indicate
reservoir quality. Importantly, the new 3D
data shows a lack of reflectivity at
Cattamarra level at Ocean Hill-1 (drilled in
1991)
which
corroborates
Strike’s
interpretation that the well was not located
optimally and areas adjacent to the primary
north-south faults represent areas of better
reservoir development.
•
Possible Ocean Hill-2 drill locations are being identified on the fast-track seismic volumes
where further processed volumes of the seismic will allow for additional geophysical work to
be conducted and increase confidence as Strike refines these proposed locations.
•
Earth Signal are completing in-depth processing of the full dataset and final seismic volumes
are expected towards the end of the year.
Arrino-Kadathinni (EP503, 504 & 505, STX 100% and operator)
•
Acquisition of the Kadathinni 2D seismic survey was completed in early June on time and
within budget. Processing of the seismic will be conducted by RealTime Seismic and final
volumes are expected to be received toward the end of the September quarter.
•
Early versions of the seismic show positive imaging at Permian level with definition of the
major fault systems that support the structural extensions from Lockyer and the Erregulla’s.
L7 Joint Venture (L7, STX 25% and non-operator)
•
The L7 Joint Venture took possession of the Ventia 106 rig for the drilling of the Booth-1
exploration well in the north Perth Basin on 22 July 2024. The well is prospective for both oil
and gas targets throughout the upper and lower Permian. It is expected to take 10 days to
move the rig to site and the Operator expects the well to be spudded on or about 31 July 20248.
Financial
•
During the quarter total gross sales were ~2.4 PJe of gas and condensate. Sales were made
up of 2.3 PJ of sales gas and 15,661 bbls of associated condensate across 2 liftings. Total sales
revenue rose 13% quarter on quarter.
8 Refer to Triangle Energy (TEG:ASX) ASX announcement dated 22 July 2024 entitled “Ventia Rig Mobilising to Booth-1 Well Location”.
7
•
Gas sales revenues for the quarter were ~$18 million (10% increase q-o-q). Averaged realised
gas prices were ~$7.82 GJ (4% increase). Condensate liftings and sales from Port Bonython
totalled ~$2.2 million (37% increase q-o-q) and averaged ~$139/bbl (18% increase q-o-q).
Total production costs year to date have averaged $0.62/GJ.
•
Capital expenditure during the quarter was $26.4 million, including the Walyering-7 drilling
and testing campaign, the Kadathinni 2D seismic acquisition and preparation for the Erregulla
Deep-1 and Booth-1 exploration wells.
•
Strike finished the quarter with a liquidity position of ~$86 million (~$39 million of cash, ~$47
million of committed, undrawn debt and $0.14 million of listed equities).
•
During the quarter Strike was not required to pay down its existing Macquarie facility whilst it
was engaged in negotiations for its proposed $153 million financing package9. Drawn debt
from this facility at the end of the quarter was $16.3 million.
•
During the quarter $239,621 in payments were made to related parties for director fees.
Revenue
Note: Net to Strike is 55% equity to 31 Dec 2023 and 100% thereafter.
Mar Q3
FY24
Jun Q4
FY24
Qtr on Qtr
change
FY23
YTD
FY24
YTD
Change
16
17.7
10%
-
47.1
-
Gas (net to Strike)
16
17.7
10%
-
41.1
-
Condensate (gross)
1.6
2.2
37%
-
5.2
-
1.6
2.2
37%
-
4.5
-
17.6
19.9
13%
-
52.3
-
17.6
19.9
13%
-
45.6
-
A$ million
Sales Revenue
Gas (gross) 10
Condensate (net to Strike)
Total Sales Revenue (gross)
Total Sales Revenue (net to Strike)
Average Realised Prices
Gas
($/GJ)
7.54
7.82
4%
-
7.45
-
Condensate
($/bbl)
118.52
130.4
10%
-
123.9
-
Mar Q3
FY24
Jun Q4
FY24
Qtr on Qtr
change
FY23
YTD
FY24
YTD
Change
Exploration & Appraisal 11
19.2
8.9
(54%)
7.8
84.5
979%
Development 12
0
19.7
N.A
43.5
27
(38%)
19.2
28.6
49%
51.4
111.4
117%
Mar Q3
FY24
Jun Q4
FY24
Qtr on Qtr
change
FY23
YTD
FY24
YTD
Change
Cash & Cash Equivalents
44.6
38.8
(13%)
129
38.8
(70%)
Undrawn Debt
46.8
46.8
-
46.8
46.8
-
91.4
85.5
(6%)
175.8
85.5
(51%)
Capital Expenditure
A$ million
Total Capital Expenditure
Liquidity
A$ million
Total Liquidity
9 Refer to footnote 4.
10 Sales gas revenue includes gas banked and not taken or produced pursuant to the ‘Take or Pay’ contract with Santos WA Ltd.
11 E & A expenditure includes long lead drilling inventory.
12 Development expenditure includes Walyering 7 drilling and associated tie back capital as well as restoration estimates.
8
Corporate & Commercial
•
During the quarter Strike announced that it has reached agreement with Macquarie Bank
Limited for a $153 million development funding package, including the refinancing of the
existing debt package, to fund production upgrades, pre-development and development
costs across its Perth Basin portfolio of assets. Provision of the facilities is subject to
execution of the definitive financing documentation 13.
•
Strike completed a minimum holding buy-back for the holders of unmarketable parcels (less
than $500) of ordinary shares 14. The final number of shares purchased under the minimum
holding buy-back was 1,452,642 ordinary shares, held by a total of 1,127 shareholders. This
represents approximately 8% of the Company’s total number of shareholders. The aggregate
value of the shares bought back was $348,634.08.
Petroleum Tenements Held at the End of the Quarter
Permit
Type
Basin
Play
Operator
(parent)
STX Interest
Gross Area
(acres)
STX Net Area
(acres)
L23 (Walyering)
Production
Perth Basin
Jurassic Wet Gas
Strike
100%
18,222
18,222
L24 (South Erregulla)
Production
Perth Basin
Permian Gas
Strike
100%
18,409
18,409
L7 (Mount Horner)
Production
Perth Basin
Permian Gas/Oil
Triangle
25%
37,021
9,255
EP469 (West Erregulla)
Exploration
Perth Basin
Permian Gas
Strike
50%
55,500
27,750
EP503
Exploration
Perth Basin
Permian Gas
Strike
100%
120,217
120,217
EP504
Exploration
Perth Basin
Permian Gas
Strike
100%
92,170
92,170
EP505
Exploration
Perth Basin
Permian Gas
Strike
100%
18,533
18,533
EP506
Exploration
Perth Basin
Permian Gas
Strike
100%
37,066
37,066
EP447
Exploration
Perth Basin
Jurassic Wet Gas
Strike
100%
127,849
127,849
EP488
Exploration
Perth Basin
Jurassic Wet Gas
Strike
100%
73,390
73,390
EP489
Exploration
Perth Basin
Jurassic Wet Gas
Strike
100%
36,572
36,572
EP495
Exploration
Perth Basin
Jurassic Wet Gas
Strike
100%
73,637
73,637
EP437
Exploration
Perth Basin
Permian Gas/Oil
Triangle
25%
176,861
44,215
PPL210 (Aldinga)
Production
Cooper Basin
Shallow Oil
Beach
50%
988
494
PEL 96
Exploration
Cooper Basin
Deep Coal
Strike
67%
668,098
444,953
This report is authorised for release by the Managing Director and Chief Executive Officer in
accordance with the Company’s Continuous Disclosure Policy.
Company Contact
Emma Alexander
Investor Relations & Corporate Manager
Strike Energy Limited
+61 419 877 137
emma.alexander@strikeenergy.com.au
Media Contacts
Paul Ryan
Sodali & Co.
+61 409 296 511
paul.ryan@sodali.com
13 Refer to footnote 4.
14 For further information, refer to ASX announcement dated 28 March 2024 entitled “Minimum Holding Share Buy-Back”.
9
Important Notices
Power Project
The development of the Power Project is contingent on, among other things, the award of Certified Reserve
Capacity (CRC) and Network Access Quantity (NAQ), satisfaction of the conditions precedent to and
financial close under the Macquarie Bank project finance facility for the Power Project (details of which
were released to ASX on 21 June 2024), execution of all required procurement contracts, and obtaining all
requisite regulatory and stakeholder permits, approvals, licences and authorisations by no later than 30
November 2024 in order to meet the construction timeline to be supplying electricity into the grid by 1
October 2026.
The forecast capital and operating expenditures and revenue for the Power Plant have been modelled
based on the assumptions and information set out or referred to in this release (including but not limited to
the Company’s announcement dated 24 June 2024), are to the level of accuracy as specified in this release,
and are subject to change. These forecasts are, by their nature, forward looking statements and subject to
the same risks as other forward looking statements (see below).
Reserves and Resources Information
Unless otherwise stated, references in this Interim Financial Report to the South Erregulla Reserves and
Resources Estimate is to the reserves and resource estimates set out in ASX announcement dated 24th
June 2024 entitled “South Erregulla Reserves”. This announcement is available to view on Strike Energy's
website at www.strikeenergy.com.au. Strike confirms it is not aware of any new information or data that
materially affects the information included in the referenced announcements and that all the material
assumptions and technical parameters underpinning the estimates in those announcements continue to
apply.
Forward looking Statements
Statements contained in this Interim Financial Report, including but not limited to those regarding the
possible or assumed future costs, projected timeframes, performance, dividends, returns, revenue, exchange
rates, potential growth of Strike, industry growth, commodity or price forecasts, or other projections and any
estimated company earnings are or may be forward looking statements. Forward looking statements can
generally be identified by the use of words such as ‘project’, ‘foresee’, ‘plan’, ‘expect’, ‘budget’, ‘outlook’,
‘schedule’, ‘estimate’, ‘target’, ‘guidance’ ‘aim’, ‘intend’, ‘anticipate’, ‘believe’, ‘estimate’, ‘may’, ‘should’, ‘will’ or
similar expressions. Forward looking statements including all statements in this document regarding the
outcomes of preliminary and definitive feasibility studies, projections, guidance on future earnings and
estimates are provided as a general guide only and should not be relied upon as an indication or guarantee
of future performance. These statements relate to future events and expectations and as such involve known
and unknown risks and significant uncertainties, many of which are outside the control of Strike. Actual
results, performance, actions and developments of Strike may differ materially from those expressed or
implied by the forward-looking statements in this Interim Financial Report. Such forward-looking statements
speak only as of the date of this document. Refer to the risk factors set out in Talon Energy Limited’s Scheme
Booklet dated 3 November 2023 in relation to the acquisition by Strike Energy (through its wholly owned
subsidiary) of all of the issued shares in Talon Energy by way of scheme of arrangement pursuant to Part 5.1
of the Corporations Act 2001 (Cth) for a summary of certain general, Strike Energy specific and acquisition
specific risk factors that may affect Strike Energy. There can be no assurance that actual outcomes will not
differ materially from these statements. Investors should consider the forward looking statements contained
in this Interim Financial Report in light of those disclosures. To the maximum extent permitted by law
(including the ASX Listing Rules), Strike and any of its affiliates and their directors, officers, employees,
agents, associates and advisers disclaim any obligations or undertaking to release any updates or revisions
to the information in this document to reflect any change in expectations or assumptions; do not make any
representation or warranty, express or implied, as to the accuracy, reliability or completeness of the
information in this document, or likelihood of fulfilment of any forward-looking statement or any event or
results expressed or implied in any forward-looking statement; and disclaim all responsibility and liability for
these forward-looking statements (including, without limitation, liability for negligence). Nothing in this
Interim Financial Report will under any circumstances create an implication that there has been no change
in the affairs of Strike since the date of this document.
10
Quarterly Activities &
Financials
Q4-FY24
Erregulla Deep-1
Cautionary note and disclaimer
Summary information
This presentation contains summary information and statements about Strike Energy Limited (ASX:STX) (Strike), its subsidiaries and their respective activities, which is current as at the date of this
presentation (unless otherwise indicated).
The information in this presentation is general in nature and does not purport to be exhaustive. For example, this presentation does not purport to contain all of the information that investors may require in
evaluating a possible investment in Strike . It has been prepared by Strike with due care but no representation or warranty, express or implied, is provided by Strike in relation to the currency, accuracy,
reliability, fairness or completeness of the information, opinions or conclusions in this presentation.
This presentation should be read in conjunction with Strike’s other periodic and continuous disclosure announcements lodged with the Australian Securities Exchange (ASX), which are available on the
ASX website (at www.asx.com.au) and the Strike website (at www.strikeenergy.com.au).
No person other than Strike has authorised or caused the issue, release, submission, distribution or provision of this presentation, or takes any responsibility for, or makes or purports to make,
any statements, representations or undertakings in this presentation. Strike, to the maximum extent permitted by law, expressly excludes and disclaims all liability (including, without limitation, any liability
arising out of fault or negligence on the part of any person) for any direct, indirect, consequential or contingent loss or damage, or for any costs or expenses, arising from the use of this presentation or its
contents or otherwise arising in connection with it. Strike does not make any representations or warranties (express or implied) to you about the currency, accuracy, reliability or completeness of the
information, opinions and conclusions in this presentation (including, without limitation, any financial information, any estimates or projections and any other financial information).
Not an offer, and not investment or financial product advice
This presentation is not a prospectus, product disclosure statement or other disclosure document under the Corporations Act, or other offering document under Australian law or any other law. This
presentation has not been lodged with the Australian Securities and Investments Commission. This presentation, and the information contained in it, is provided for information purposes only and is not an
offer or solicitation or an invitation or recommendation to subscribe for, acquire or buy securities of Strike, or any other financial products or securities, in any place or jurisdiction.
This presentation may not be released to US wire services or distributed in the United States. This presentation does not constitute an offer to sell, or the solicitation of an offer to buy, any securities in
the United States or any other jurisdiction in which such an offer would be unlawful. The securities referred to in this document have not been, and will not be, registered under the US Securities Act of 1933
(US Securities Act) and may not be offered or sold in the United States except in transactions exempt from, or not subject to, the registration requirements of the US Securities Act and applicable US