Operational Update and Listing Rule 3.10A Notice
• Strike has completed commissioning of upstream gas facility and power station
package pending compliance testing with AEMO
• Pre-commissioning site inspections of downstream switchyards completed by Strike
and Western Power
• Western Power expected to commence downstream commissioning on 21 July 2026
• Carnarvon Energy shares to be released from voluntary escrow on 25 July 2026
Strike Energy Limited (Strike - ASX: STX) provides an update on operational activities at the South
Erregulla Power Plant (SEPP).
Strike has completed commissioning of the upstream gas facilities and power station package,
which have now been placed into preservation mode as planned pending Hold Point Testing to be
conducted as part of the Generator Performance Standard compliance testing process with the
Australian Energy Market Operator (AEMO).
Strike and Western Power completed a second pre-commissioning site inspection of the
downstream switchyards on 14 July 2026. Subject to completion of the remaining construction and
readiness activities, Western Power is expected to commence its commissioning activities on 21
July 2026.
Chief Executive Officer and Managing Director, Shelley Robertson, said:
“Pending compliance testing with AEMO, we have now completed commissioning of the upstream
gas delivery facilities and power station package and are focused on completing the remaining
downstream switchyard works ahead of Western Power's commissioning activities. The revised
commencement date reflects the normal co-ordination of construction completion, inspections and
commissioning resources that occurs on projects of this nature, and the project continues to
progress well through its final stages.”
16 July 2026 ASX: STX The Company Announcement Officer ASX Ltd via electronic lodgement
Upstream SEPP – Commissioning complete and placed in preservation program
2
Downstream SEPP – CRY and KGN Switch Yards nearing completion
Permanent signage installed at South Erregulla Power Plant
3
Corporate Update
Strike also advises that, in accordance with ASX Listing Rule 3.10A, the following securities will be
released from voluntary escrow on 25 July 2026 (‘Shares’).
Number of Shares Type Release Date
716,279,985 Fully paid ordinary shares 25 July 2026
The escrow arrangements formed part of the transaction announced on 22 July 2025. The release
of the securities from escrow does not result in any new securities being issued and does not affect
the Company's issued capital.
This announcement has been authorised for release by the Board of Directors.
Company & Media Contact
Shelley Robertson
CEO & MD
Strike Energy Limited
shelley.robertson@strikeenergy.com.au
Important Notices
Forward looking Statements
Statements contained in this release, including but not limited to those regarding the possible or assumed future costs,
projected timeframes, performance, dividends, returns, revenue, exchange rates, potential growth of Strike, industry
growth, commodity or price forecasts, or other projections and any estimated company earnings are or may be
forward looking statements. Forward looking statements can generally be identified by the use of words such as
‘project’, ‘foresee’, ‘plan’, ‘expect’, ‘budget’, ‘outlook’, ‘schedule’, ‘estimate’, ‘target’, ‘guidance’, ‘aim’, ‘intend’,
‘anticipate’, ‘believe’, ‘estimate’, ‘may’, ‘should’, ‘will’ or similar expressions. Forward looking statements including all
statements in this document regarding the outcomes of preliminary and definitive feasibility studies, projections,
guidance on future earnings and estimates are provided as a general guide only and should not be relied upon as an
indication or guarantee of future performance. These statements relate to future events and expectations and as such
involve known and unknown risks and significant uncertainties, many of which are outside the control of Strike. Actual
results, performance, actions and developments of Strike may differ materially from those expressed or implied by the
forward-looking statements in this release. Such forward-looking statements speak only as of the date of this document.
Refer to the risk factors starting on page 31 of the 2025 Annual Report for a summary of certain general and Strike
Energy specific risk factors that may affect Strike Energy. There can be no assurance that actual outcomes will not differ
materially from these statements. Investors should consider the forward looking statements contained in this release in
light of those disclosures. To the maximum extent permitted by law (including the ASX Listing Rules), Strike and any of
its affiliates and their directors, officers, employees, agents, associates and advisers disclaim any obligations or
undertaking to release any updates or revisions to the information in this document to reflect any change in
expectations or assumptions; do not make any representation or warranty, express or implied, as to the accuracy,
reliability or completeness of the information in this document, or likelihood of fulfilment of any forward-looking
statement or any event or results expressed or implied in any forward-looking statement; and disclaim all responsibility
and liability for these forward-looking statements (including, without limitation, liability for negligence). Nothing in this
release will under any circumstances create an implication that there has been no change in the affairs of Strike since
the date of this document.
Share your feedback
Discover