Southern Cooper Basin Gas Project Operations Update
Released
Released
Announcement PDF
ASX Announcement
22 December 2015
The Company Announcement Officer ASX Ltd
via electronic lodgement
SOUTHERN COOPER BASIN GAS PROJECT
OPERATIONS UPDATE
•
Record gas flows achieved by the Klebb Phase 3 pilot
Strike Energy Limited (ASX:STX) (“Strike”) is pleased to provide an update on operations at its Southern
Cooper Basin Gas Project in PEL 96 (Strike 66.67% and Operator, Energy World Corporation (ASX:EWC)
33.33%).
Klebb Production Test Update
Excellent progress towards commercial gas flows continues to be made by the Klebb pilot with
particularly pleasing rates achieved by the Klebb 2 and 3 wells.
Klebb 3 – December 2015
Strike Energy Limited ABN 59 078 012 745
www.strikeenergy.com.au
P: +61 2 9397 1420
E: strike@strikeenergy.com.au
120B Underwood Street, Paddington NSW 2021
ASX Announcement
22 December 2015
Klebb 2 and Klebb 3 have performed well with strong, consistent gas flows and stable water
production. Work is ongoing to optimise the capacity of the Klebb 2 and 3 jet pumps through
adjustments to the downhole pump and surface equipment configuration to maximise performance.
The beam pump at Klebb 1 has operated with very high availability and the well is producing gas
consistently. However, we have not yet been able to achieve stable downhole gas separation to
prevent gas from entering the pump and tubing. As a result, the pump operating rate has had to be
limited to minimise the risk of a pump failure.
Observations
The testing program has achieved water flow rates and bottom hole pressure reductions required to
create and sustain low pressure zones around each of the wells. Significant increases in gas flow rates
are recorded as these low pressure zones expand away from the wells and the volume of coal below
critical gas desorption pressure increases. The rate at which the low pressure zones grow is driven by
the rate at which water is produced from the reservoir and the time required to reach commercial
gas flow rates simply depends on how quickly the low pressure zones expand.
Production testing will continue over the Christmas and New Year period with a focus on maximising
water and gas flow rates.
Managing Directors Comment
“We are really excited by the performance of the Klebb Phase 3 pilot wells. We are building momentum
and fully expect that the wells will demonstrate productive capacity exceeding our threshold
commercial gas rates.”
Yours faithfully
DAVID WRENCH
Managing Director