DUG Australia Conference Presentation
Released
Released
Announcement PDF
ASX Announcement
29 July 2015
The Company Announcement Officer ASX Ltd
via electronic lodgement
DUG AUSTRALIA CONFERENCE PRESENTATION – JULY 2015
Please find attached a presentation to be given by Mr David Wrench at the DUG Australia
conference to be held at the Royal International Conference Centre in Brisbane today.
Yours faithfully
Sean McGuinness
Chief Financial Officer & Company Secretary
Strike Energy Limited ABN 59 078 012 745
www.strikeenergy.com.au
P: +61 2 9397 1420
E: strike@strikeenergy.com.au
120B Underwood Street, Paddington NSW 2021
STRIKE ENERGY LIMITED
DUG CONFERENCE
July 2015
Strike Energy Limited - DUG Presentation, July 2015
1
DUG Conference: Strike Energy Limited
Eastern Australian gas supply - are there new ‘sweet spots’ out there?
Strike’s Southern Cooper Basin Gas Project - an emerging ‘sweet spot’
Strike Energy Limited - DUG Presentation, July 2015
2
Eastern Australian Gas Supply: Are there new ‘sweet spots’ out there?
“An unconventional resource ’sweet spot’ is that part of the resource that has the
lowest unit cost economics and maximum value.”
GAS
RESOURCE
GAS
MARKET
SUPPLY COST
VALUE
CREATION
Core Qld CSG
elsewhere ?
Strike Energy Limited - DUG Presentation, July 2015
3
Gas Resource: Eastern Australian hydrocarbon basins
Significant unconventional gas resources exist in the Cooper Basin and Queensland coal fields.
Mount Isa
Bowen and Surat Basins
Gladstone
Cooper-Eromanga Basin
Moomba
Brisbane
Gunnedah Basin
Sydney
Adelaide
Melbourne
Gippsland Basin
Otway Basin
Bass Basin
Hobart
gas pipelines
No unconventional ‘sweet spots’ have been identified outside of core QLD CSG fields to date
Strike Energy Limited - DUG Presentation, July 2015
4
Eastern Australian Gas Market: 20-year total demand
Over the 20-year period from 2020 to 2040, 40 Tcf of gas will be required to meet demand.
Export LNG projects will create 75% of this demand.
(1)
Domestic demand
LNG Export demand (1)
10,000 PJ
30,000 PJ
Current LNG market forecast demand
LNG projects will dominate the gas market
Strike Energy Limited - DUG Presentation, July 2015
5
Supply cost: Cost curve
Strike’s analysis highlights the steepness of the East Australian gas supply cost curve.
The discovery and development of new large scale lower cost gas resources could substantially lower input costs for gas users by
substituting higher cost reserves.
Queensland JV CSG ‘Equity‘
gas - Tier 3
Estimated unit cost of supply $/GJ
Cooper Basin
Conventional
Queensland JV CSG
‘Equity‘ gas - ‘sweet spots’
Queensland CSG
Third Party
Queensland JV CSG
‘Equity‘ gas - Tier 2
Other Victorian
Gippsland JV
Eastern Australian demand (PJ)
10,000
20,000
30,000
Average supply cost
40,000
50,000
Current 20 years demand forecast
Gippsland Basin JV
Queensland JV CSG
‘equity’ gas sweet spots
Other Victorian
Queensland JV CSG
‘equity’ gas – Tier 2
Queensland JV CSG
‘equity’ gas – Tier 3
Queensland CSG third
party
Cooper Basin
conventional
New large scale lower cost resources are needed to displace higher cost gas
Strike Energy Limited - DUG Presentation, July 2015
6
Supply cost: Liquefaction business
LNG liquefaction projects are merchant gas processing businesses. These businesses must source the lowest cost gas supply from the market,
be that ‘equity’ or third party gas.
The cost of gas supply is the one area of the business value chain that can be highly influenced by ongoing ‘make’ or ‘buy’ decisions
throughout the operating life of the liquefaction plant.
LIQUEFACTION BUSINESS
BUY GAS
PROCESS GAS
SELL LNG
Gas Supply
[Equity or Third Party]
Gas processing
[Liquefaction]
LNG transport
[Shipping]
~ $4 BILLION P.A (1)
~ $500 MILLION P.A
~ $500 MILLION P.A
HIGH
LOW
LOW
LOW
Sourcing lowest cost gas
Low opex variability
Standard int. shipping rates
Price defined by contract terms
LNG sales
[Customers]
% OF TOTAL COST
ABILITY TO INFLUENCE
COMMERCIAL
OUTCOMES
[Plant operating phase]
(1)
Based on an estimated 500 PJ/annum at a gas sales price of $8/PJ.
Gas supply is the primary business cost
Strike Energy Limited - DUG Presentation, July 2015
7
Supply cost: Focus moving to cost of supply
Dramatic changes in the Eastern Australia gas demand profile have been driven by construction of six LNG trains at Gladstone. These
trains will account for 30 Tcf of the 40 Tcf demand profile over the next twenty years.
During the ramp-up phase the focus is on establishing rate of gas supply into the plants to ensure offtake commitments can be met.
Post ramp-up phase the focus will move to the cost of gas supply to maximise future operating cash flows.
9 million tonne per annum LNG facility (two trains) – 500 PJ/annum – sensitivity to cost of gas supply
Revenue
Costs
+ $5 billion
pa
Margin
∆ $1/GJ gas
supply cost
Margin
-$1/GJ
+$1/GJ
∆ $1/GJ gas
supply cost
Gas Supply
+ $500 million pa
operating cash flow
Liquefaction
Shipping
Massive incentive for LNG facilities to source lowest cost gas supply
Strike Energy Limited - DUG Presentation, July 2015
8
Eastern Australian Gas Supply: Summary
Gas demand
~40 Tcf over twenty years; LNG the dominant gas buyer
LNG merchant business
Operating cash flows highly leveraged to gas supply cost
Cost curve
Eastern States gas market cost curve is very steep
Addressable market
10 - 20 Tcf addressable market for competitive new gas supply
Market opportunity
The lower the cost, the larger the market
Strike’s strategy is to be the leading independent gas supplier to the Eastern Australian gas market
Strike Energy Limited - DUG Presentation, July 2015
9
Gas resource: Strike’s Southern Cooper Basin Gas Project
Prospective
Resource
PEL 96
4,492 Bcf*
PEL 96 Phase
One Area
1,123Bcf*
Moomba
2C
Contingent
Resource*
Marsden 1
104 Bcf
Davenport 1
PEL 94
STX 35%
PEL 95
STX 50%
Mount Isa
Gladstone
Le Chiffre 1
Klebb production
testing area
Moomba
PELA 640
STX 100%
Brisbane
PEL 96
STX 66.67%
0
20
Sydney
Adelaide
Kilometers
Melbourne
PEL 96 Phase One Area
Strike Phase One Area wells drilled
Gas Pipeline
Strike Wells Drilled
Oil Pipeline
PEL 96 Offset Wells
Strzelecki Track
PEL 96 and PELA - STX Operated
Hobart
* Mean estimate (net to Strike determined on a probalistic basis) per ASX announcement dated 19 Feb 2014 and adjusted for announced contingent
resource estimate per ASX announcement dated 27 April 2015.
** The estimated quantities of petroleum that may potentially be recovered by the application of a future development project relate to
undiscovered accumulations. These estimates have both an associated risk of discovery and a risk of development. Further exploration
appraisal and evaluation is required to determine the existence of a significant quantity of potentially movable hydrocarbons.
PEL
Net STX Acres
PEL 94
77,925
PEL 95
160,248
PEL 96
443,880
PELA 640
850,786
Total
1,532,839
Strike has an ideally positioned long-life multi-Tcf resource
directly connected to the ~40 Tcf Eastern Australian gas market
Strike Energy Limited - DUG Presentation, July 2015
10
Unit Cost of Supply: Economics of Strike’s Southern Cooper Coals
Strike’s demonstrated cost structure will drive competitive unit production costs for wells that recover greater than 3PJ.
Production type curve - long stable phase
5
10
Years
Avg daily rate
Cumulative production (PJ)
Stable
production
phase
PEL 96 well full cycle costs (undiscounted) (1)
15
Well capex (drill/complete/connect)
$3.5m
Other capex (gathering/processing) (1) + Opex
$13.5m
Total
$17.0m
20
Cumulative production (PJ)
(1)
Based on current Strike estimates
Ex-field gas costs
Ex-field gas cost
($/GJ)
5.50
Higher EURs
drive lower unit costs
3.50
3
4
5
EUR/well (PJ)
Strike is targeting a competitive positioning on the Eastern Australian gas cost curve
Strike Energy Limited - DUG Presentation, July 2015
11
Unit cost of supply: Cost curve
Strike’s Southern Cooper Basin Gas Project has the potential to be a low cost gas producer.
1
Eastern Australian demand (PJ)
10,000
1
20,000
New STX target supply
Estimated unit cost of supply $/GJ
Strike Southern Cooper
PEL 96
30,000
Average supply cost
40,000
50,000
Current 20 years demand forecast
Gippsland Basin JV
Queensland JV CSG
‘equity’ gas sweet spots
Other Victorian
Strike’s Southern Cooper
Basin Gas Project
Cooper Basin
conventional
Queensland JV CSG
‘equity’ gas – Tier 2
Queensland JV CSG
‘equity’ gas – Tier 3
Queensland CSG third
party
The lower the unit cost the larger the market opportunity
Strike Energy Limited - DUG Presentation, July 2015
12
Value Creation: Klebb 1 – flow test results
The Klebb 1 single stage flow test is a small scale test of potential flow rates achievable from a commercial development well.
Development Well
Target commercial gas
flow rate -> 1,200 Mscfd
Klebb 1 Flow Test
Three completion zones
>120,000 lbs frac per zone
300
Mscfd
Single stage Vu Upper
<60,000 lbs frac
Vm3
600
Mscfd
Vu Upper
Vu lower
300
Mscfd
Three completion stages
(development well)
One completion stage
(Klebb 1)
Klebb 1 results need to be scaled to assess commercial potential
Strike Energy Limited - DUG Presentation, July 2015
13
Value Creation: Future cash flow potential
Strike is targeting a low unit cost of supply that will deliver strong operating cash flows in the stable production phase. Future value will
be driven by per well operating cash flows and the size of the resource in Strike’s permit areas that could ultimately be commercialised.
PEL 96 - Target cash flow per well
PEL 96 - Operating cash flow potential (1)
$480m pa
EBITDA
5
Avg daily rate
10
Years
Cumulative production (PJ)
Stable
production
phase
15
$240m pa
20
Cumulative production (PJ)
$60m pa
• 67% of a well’s gas is typically recovered
over a long stable production phase
50
wells
• At a stable rate of 1,200 Mscf per day a well
has the potential to generate operating cash
flow of $1.2m per year
(1)
200
wells
400
wells
Wells
Based on Strike estimates with that each well generating $1.2 M in operating cashflow p.a.
Portfolio of 50 wells could generate EBITDA of ~$60m per year
Strike Energy Limited - DUG Presentation, July 2015
14
Strikes Southern Cooper Basin Gas Project: An emerging ‘sweet spot’
GAS
RESOURCE
PEL 96 prospective
resource
4.5 Tcf (net STX)
Strike Energy Limited - DUG Presentation, July 2015
GAS
MARKET
UNIT COST
OF SUPPLY
VALUE
CREATION
Cost of supply defines
available market
Full life cycle
well cost / EUR
Operating
cash flow
10 - 20 Tcf addressable
market for competitive
new gas supply
STX potential ex-field
cost < $4.50/GJ
STX potential >$1.2m
EBITDA per well p.a.
Current appraisal program
Future development
15
Important Notice
This presentation does not constitute an offer, invitation or recommendation to subscribe
for, or purchase any security and neither this presentation nor anything contained in it shall
form the basis of any contract or commitment.
Reliance should not be placed on the information or opinions contained in this
presentation. This presentation does not take into consideration the investment objectives,
financial situation or particular needs of any particular investor. Any decision to purchase
or subscribe for any shares in Strike Energy Limited should only be made after making
independent enquiries and seeking appropriate financial advice.
No representation or warranty, express or implied, is made as to the fairness, accuracy,
completeness or correctness of the information, opinions and conclusions contained in
this presentation. To the maximum extent permitted by law, Strike Energy Limited and its
affiliates and related bodies corporate, and their respective officers, directors, employees
and agents disclaim liability (including without limitation, any liability arising from fault
or negligence) for any loss arising from any use of or reliance on this presentation or its
contents or otherwise arising in connection with it.
Statements contained in this presentation, including but not limited to those regarding the
possible or assumed future costs, performance, dividends, returns, production levels or
rates, oil and gas prices, reserves, potential growth of Strike Energy Limited, industry growth
or other projections and any estimated company earnings are or may be forward looking
statements.
Such statements relate to future events and expectations and as such involve known and
unknown risk and uncertainties, many of which are outside the control of Strike Energy
Limited. Actual results, actions and developments may differ materially from those
expressed or implied by the statements in this presentation.
Subject to any continuing obligations under applicable law and the Listing Rules of ASX
Limited, Strike Energy Limited does not undertake any obligation to publicly update or
revise any of the forward looking statements in this presentation or any changes in events,
conditions or circumstances on which any such statement is based.
Strike Energy Limited - DUG Presentation, July 2015
Contingent Resource Estimate
DeGolyer and MacNaughton was engaged by Strike to undertake an Independent Review
of the gas resource in PEL 96 based on the data and information acquired to date by Strike
from the drilling and flow testing programs carried out at the Le Chiffre 1 and Klebb 1, Klebb
2 and Klebb 3 wells.
DeGolyer and MacNaughton has estimated a contingent gas resource on a probalistic basis for
the initial zones that have been flow tested within the Le Chiffre 1 and Klebb 1 wells. As these
zones only represent a portion of the net coal encountered at these locations, successful flow
testing of additional zones will enable an increased contingent resource to be booked.
The table below summarises the Contingent Resource Estimates.
Contingent Gas Resource Estimates - PEL 961
Well
1C2
2C2
3C2
Productive area (acres)
2,171
2,938
3,931
Le Chiffre 1 - Patchawarra Vu Upper
and Vu Lower zones (bcf)
62.9
93.2
132.4
Klebb 1 - Patchawarra Vu Upper zone
9 (bcf)
42.1
62.2
93.3
Total Gross Contingent Resource (bcf)
105.00
155.4
225.7
1.
Contingent Resource Estimates have been prepared in accordance with the Petroleum Resources
Management System “PRMS”. Contingent Resource Estimates are those quantities of gas
(produced gas less carbon dioxide and fuel gas) that are recoverable from known accumulations
but which are not yet considered commercially recoverable.
2.
1C, 2C and 3C estimates in this table are P90, P50 and P10 respectively for each well and have
been summed arithmetically
3.
Net to Strike’s 66.7% interest in PEL 96
16
Important Notice
Competent Persons Statement
The information in this presentation that relates to the PEL 96 contingent resources estimate has
been taken from the independent reports as prepared by DeGolyer and MacNaughton, a leading
independent international petroleum industry consultancy firm, and has been reviewed by Mr
Chris Thompson (Chief Operating Officer of the Company). All other reported resource and or
reserves information in this presentation is based on, and fairly represents, information prepared
by, or under the supervision of Mr Thompson.
Mr Thompson holds a Graduate Diploma in Reservoir Evaluation and Management and
Bachelor of Science Degree in Geology. He is a member of the Society of Petroleum Engineers
and has worked in the petroleum industry as a practicing reservoir engineer for over 20 years.
Mr Thompson is a qualified petroleum reserves and resources evaluator within the meaning of
the ASX Listing Rules and consents to the inclusion in this release of the resource and or reserves
information in the form and context in which that information is presented.
About DeGolyer and MacNaughton
The information contained in this release pertaining to the PEL 96 contingent resources
estimate is based on, and fairly represents, information prepared under the supervision of Mr
Paul Szatkowski, Senior Vice President of DeGolyer and MacNaughton. Mr Szatkowski holds a
Bachelor of Science degree in Petroleum Engineering from Texas A&M, has in excess of 40 years
of relevant experience in the estimation of reserves and contingent resources, and is a member
of the International Society of Petroleum Engineers and the American Association of Petroleum
Geologists. Mr Szatkowski is a qualified petroleum reserves and resources evaluator within
the meaning of the ASX Listing Rules and consents to the inclusion of the contingent resource
estimate related information in the form and context in which that information is presented.
Strike Energy Limited - DUG Presentation, July 2015
17
Share your feedback
Discover