Follow the construction journey of Strike's 85MW Peaking Gas Power Plant - milestones, images and progress updates in one place.

Nameplate Capacity

85 MW

Asset Type

Gas Fired Peaking Power Plant (fast-start reciprocating engines)

Grid

South West Interconnected System (SWIS)

Location

Arrowsmith East, WA

Project: South Erregulla Peaking Power Plant (SEPP) • Last updated: 14 October 2025

Overall construction progress

0%

Timeframes and activities shown are indicative and subject to approvals, supply chains and construction conditions.

Milestones

Complete

Site preparation & civil works

Q1–Q3 2025

Bulk earthworks, fencing, laydown, internal access, and foundations complete.

Complete

South Erregulla-1 Well Workover

Q3 2025

Workover to ensure production readiness; clean up flow and production simulation has been completed in readiness for gas supply to the power plant.

In progress

Structural, Mechanical, Piping, Electrical & Instrumentation

Q3–Q4 2025

Cable trays, conduits, earthing and mechanical fit-out underway across plant areas.

In Progress

Engine delivery & placement

Q3-Q4 2025

20x Jenbacher 4.5 MW reciprocating engines shipped from Austria to Fremantle and trucked to site to be installed in engine hall.

Planned

Switchyard & Transmission Construction

Q4 2025-Q2 2026

Engineering on 15 km transmission line ongoing, work for switchyards and connection under tender.

Planned

Commissioning & performance testing

Q3 2026

System energisation, safety verifications and performance testing prior to commercial readiness.

Photo Gallery

Announcements

0 results