Follow the construction journey of Strike's 85MW Peaking Gas Power Plant - milestones, images and progress updates in one place.

Nameplate Capacity

85 MW

Asset Type

Gas Fired Peaking Power Plant (fast-start reciprocating engines)

Grid

South West Interconnected System (SWIS)

Location

Arrowsmith East, WA

Project: South Erregulla Peaking Power Plant (SEPP) • Last updated: 19 November 2025

Overall construction progress

0%

Timeframes and activities shown are indicative and subject to approvals, supply chains and construction conditions.

Milestones

Complete

Site preparation & civil works

Q1–Q3 2025

Bulk earthworks, fencing, laydown, internal access, and foundations complete.

Complete

South Erregulla-1 Well Workover

Q3 2025

Workover to ensure production readiness; clean up flow and production simulation has been completed in readiness for gas supply to the power plant.

Complete

Structural, Mechanical, Piping, Electrical & Instrumentation

Q3–Q4 2025

Structural, Mechanical, Piping, Electrical and Instrumentation (SMPEI) GWES completed installation of all radiators and positioned all generators and alternators inside the engine hall.

Complete

Engine delivery & placement

Q3-Q4 2025

20x Jenbacher 4.5 MW reciprocating engines shipped from Austria to Fremantle on site to be installed in engine hall.

In Progress

Switchyard & Transmission Construction

Q4 2025-Q2 2026

Bulk earthworks contractor (Lenane’s) mobilised to site and commenced work on CRY and KGN Switchyards.

Planned

Commissioning & performance testing

Q3 2026

System energisation, safety verifications and performance testing prior to commercial readiness.

Photo Gallery

Announcements

0 results